Tirsvad 1d35410b8d Add planning baseline: BC, SA, PP and two gateways
Create the Business Case, Stakeholder Analysis (S01 course participant,
S02 Udemy coursists, S03 GitHub viewers), Project Plan and the milestone
documents MIL-001 (project setup, 6 tasks) and MIL-002 (game
implementation, 8 tasks) for the console Blackjack game.

Register PP and MIL in the artifact registry, set the PO language to en,
and link the synced Gitea milestones in the Gateway Schedule.

Refs #1
Refs #2
Refs #3
Refs #4
Refs #5
Refs #6
Refs #7
Refs #8
Refs #9
Refs #10
Refs #11
Refs #12
Refs #13
Refs #14
2026-10-04 21:38:09 +08:00

2.3 KiB
Raw Permalink Blame History

Business Case (BC)

Cite in CrossReference only if the instance exists (new-artifact.sh checks this for you):

  • SA — Stakeholders section — cite S-IDs instead of re-describing roles
  • BMC — Cost–Benefit Assessment must agree with its cost/revenue blocks
  • BPMN — Forward: the process that realizes the objectives
  • KPI — Success Criteria — each criterion is operationalized by a KPI
  • UCD — Forward: scope expressed as actors and goals

Required sections (after Metadata / Version History)

In this order:

  1. Executive Summary — one paragraph framing the problem and the proposed solution.
  2. Methodological and Standards Foundation — states the methodology (e.g. Larman's Applying UML and Patterns) and quality standards (e.g. ISO/IEC 25002/25010/25019) the rest of the document and downstream artifacts are built on.
  3. Problem Statement — the recurring problems that justify the project.
  4. Business Opportunity — what becomes possible if the problem is solved.
  5. Objectives — concrete, verifiable statements of what the project will achieve.
  6. Scope — split into ## In Scope and ## Out of Scope subsections.
  7. Expected Benefits — split into ### Tangible Benefits and ### Intangible Benefits.
  8. Strategic Alignment — how the project supports organizational goals.
  9. Success Criteria — a table with explicit, measurable targets (not aspirations).
  10. Risks — a table with Risk | Impact | Mitigation columns; every risk must have a mitigation.
  11. Assumptions — bullet list, kept distinct from Constraints.
  12. Constraints — bullet list, kept distinct from Assumptions.
  13. Cost–Benefit Assessment — a table (Costs | Benefits); may be qualitative if explicitly justified.
  14. Stakeholders — a table referencing exact stakeholder IDs from the project's Stakeholder Analysis (e.g. S01, S07) if SA exists per the CrossReference check above. Never re-describe stakeholder roles inline instead of citing their IDs — this is the single most common defect found when reviewing Business Cases (see QC-BC-001's Common Defects).
  15. Recommendation — a single, unambiguous "proceed" or "do not proceed" statement.