Add planning baseline: BC, SA, PP and two gateways

Create the Business Case, Stakeholder Analysis (S01 course participant,
S02 Udemy coursists, S03 GitHub viewers), Project Plan and the milestone
documents MIL-001 (project setup, 6 tasks) and MIL-002 (game
implementation, 8 tasks) for the console Blackjack game.

Register PP and MIL in the artifact registry, set the PO language to en,
and link the synced Gitea milestones in the Gateway Schedule.

Refs #1
Refs #2
Refs #3
Refs #4
Refs #5
Refs #6
Refs #7
Refs #8
Refs #9
Refs #10
Refs #11
Refs #12
Refs #13
Refs #14
This commit is contained in:
2026-10-04 21:38:09 +08:00
parent 52febca25e
commit 1d35410b8d
123 changed files with 5978 additions and 0 deletions
+68
View File
@@ -0,0 +1,68 @@
# @TITLE@
## Metadata
| Key | Value |
| --- | --- |
| ID | @ID@ |
| CrossReference | @CROSSREF@ |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| @DATE@ | Accepted | @AUTHOR@ | <reviewer S-ID> | Initial version | pending |
---
## Purpose
Defines how this project applies Quality Criteria (QC) checklists to real
artifact instances, producing SQA Review Records and Go/No-Go decisions.
## ARB Review Workflow
1. **Submission** — the artifact owner submits an instance for review,
identifying its type's QC checklist (`framework/qc/qc-*.md`).
2. **QC Checklist Review** — the assigned reviewer (see RACI) applies the
checklist criterion by criterion.
3. **Review Record** — the reviewer documents the outcome as an SQA Review
Record (`RC-*` under `docs/sqa/reviews/`).
4. **Go/No-Go Decision** — the Accountable role for the artifact category
decides; contested or cross-cutting cases escalate to the ARB Chair.
5. **Sign-off** — on **Go**, the artifact's `## Version History` gets an
`Accepted` row (the previous row becomes `Deprecated`). On **Go-with-conditions**, status stays `Proposed` until
the Action Items are closed. On **No-Go**, the artifact returns to its
owner.
6. **Traceability Update** — the Traceability Matrix is updated with the
instance and its `RC-*` reference.
## RACI by Artifact Category
Fill every cell with stakeholder IDs from the Stakeholder Analysis (`S<NN>`),
never role names.
| Artifact Category | Responsible (runs the review) | Accountable (Go/No-Go owner) | Consulted | Informed |
| --- | --- | --- | --- | --- |
| Strategic (Stakeholder Analysis, Business Case, BMC) | S<NN> | S<NN> | S<NN> | S<NN> |
| Process/Business (BPMN, KPI, Milestones/Gateways) | S<NN> | S<NN> | S<NN> | S<NN> |
| Requirements (Use Case Diagram, User Story, Use Case) | S<NN> | S<NN> | S<NN> | S<NN> |
| Modeling/Design (Domain Model, SSD, Operation Contract, Sequence Diagram, DCD, ERD) | S<NN> | S<NN> | S<NN> | S<NN> |
Cross-cutting escalations and disputed verdicts are Accountable to the ARB
Chair (`S<NN>`), overriding the category-level Accountable role.
## Escalation Rules
- A **No-Go** verdict, or any disagreement between the Responsible reviewer
and the category's Accountable owner, escalates to the ARB Chair.
- A reviewer may not review an instance they authored.
- Repeated No-Go verdicts (2 or more) on the same artifact type trigger a
review of the corresponding `QC-*` checklist itself.
## Cadence
- Reviews are triggered per artifact instance as it is produced or revised.
- QC checklists are reviewed annually.
---