| 1 |
The plan states its start date, end date and the constraint it must fit |
Pass |
Purpose and Planning Assumptions state the window 2026-10-28 to 2026-11-06 and that the Business Case sets no deadline. |
| 2 |
Every milestone or gateway is listed once with its document, decision date and owner |
Pass |
Gateway Schedule lists MIL-001 to MIL-008 once each with document link, decision date and owner S01. |
| 3 |
Every decision date lies inside the plan's window and is consistent with the dates in the linked MIL-* document |
Pass |
Decision dates equal the Target Date of each MIL document and lie inside the window. |
| 4 |
Every in-scope item of the Business Case is delivered at a named gateway (scope coverage) |
Pass |
Scope Coverage maps every In Scope item to a gateway. |
| 5 |
Dependencies between gateways are stated, acyclic and consistent with the schedule order |
Pass |
Dependencies show the chain MIL-001 to MIL-008; the schedule order agrees. |
| 6 |
The plan states what happens to later gateways and to the end date when a gateway is No-Go |
Pass |
Dependencies state that a No-Go stops later gateways and that S01 decides a move of the end date. |
| 7 |
Owners, reviewers and escalation roles use Stakeholder Analysis IDs and match the governance RACI |
Pass |
Owner S01 and reviewer S02 come from SA-001; no governance document exists in this project. |
| 8 |
Planning assumptions are listed with their source, and a changed baseline is recorded with its reason |
Pass |
Planning Assumptions list their source; no baseline was changed. |
| 9 |
Plan risks are listed with impact and a mitigation, and trace to Business Case risks where they come from there |
Pass |
Plan Risks has four risks with impact and mitigation, linked to the Business Case risks. |
| 10 |
Open issues are listed, and none contradicts a statement elsewhere in the plan |
Pass |
Open Issues lists the repository question, the missing deadline and the acceptance note; none contradicts the plan. |
| 11 |
Each gateway's main deliverable is stated and matches the deliverable of its MIL-* document |
Pass |
Main deliverables in the schedule match the Deliverable section of each MIL document. |
| 12 |
Gateways that deliver user stories name them, and those that do not say why |
Pass |
Planning Assumptions say stories are skipped (ADR-0001); the Stories column says why for each gateway. |
| 13 |
The schedule view (table, Gantt) and the dependency view agree with each other |
Pass |
The Gantt bars and the table dates are the same; the chain matches the dependency list. |
| 14 |
Each gateway is linked to its issue-tracker milestone, or marked as not yet synced |
N-A |
No Milestones exist on the git host yet; the Milestone column is blank on purpose until the publish workflow runs. |
| 15 |
The plan is a singleton: one Project Plan per project, changes recorded in Version History |
Pass |
PP-001 is the only Project Plan; the change is in Version History. |