Project Plan: Snack and Lift Booking Bot

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005, MIL-006, MIL-007, MIL-008
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-28 Accepted Jens Tirsvad Nielsen S01 Initial version: eight gateways 50e8331

Purpose

This plan schedules eight gateways (MIL-001 to MIL-008) that take the Snack and Lift booking bot from an accepted baseline to a documented, tested and published repository. The Business Case sets no deadline, so the window 2026-10-28 to 2026-11-06 is a planning assumption of this plan. Each gateway ends in a decision and a deliverable and is delivered by one pull request on its own branch.

Planning Assumptions

  • Week 1 starts 2026-10-28; the plan ends by 2026-11-06 (a planning assumption, see Open Issues).
  • Phase length: one to two days per gateway. Gateways 003 to 007 follow the Udemy lecture steps 1 to 9.
  • One branch and one pull request per gateway, each closing the issues of its tasks.
  • The user stories and use case steps of the journey are skipped for this project (ADR-0001), so no gateway lists stories.
  • Autonomous mode: S01 accepts this plan in chat; the AI acts as stand-in reviewer (S02) and records it in each RC-*.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Baseline and repository set-up MIL-001 2026-10-28 2026-10-28 S01 none (documents) Accepted baseline, ADRs, repository description and topics
Project scaffold and tooling MIL-002 2026-10-28 to 2026-10-29 2026-10-29 S01 none (technical tasks) pyproject.toml, layout, .gitignore, Doxyfile, README, Docker image
Lecture steps 1 and 2 MIL-003 2026-10-29 to 2026-10-30 2026-10-30 S01 none (technical tasks) Chrome profile, navigation, login(), screenshots 1 and 2
Lecture steps 3 and 4 MIL-004 2026-10-30 to 2026-10-31 2026-10-31 S01 none (technical tasks) Card parsing, booking, state checks, screenshots 3 and 4
Lecture steps 5 and 6 MIL-005 2026-10-31 to 2026-11-01 2026-11-01 S01 none (technical tasks) Counters, summary, Tuesday and Thursday list, screenshots 5 and 6
Lecture steps 7 and 8 MIL-006 2026-11-01 to 2026-11-02 2026-11-02 S01 none (technical tasks) My Bookings verification, time travel, screenshots 7 and 8
Lecture step 9 MIL-007 2026-11-02 to 2026-11-04 2026-11-04 S01 none (technical tasks) retry, resilient login, book_class, get_my_bookings, screenshot 9
Documentation, wiki and release MIL-008 2026-11-04 to 2026-11-06 2026-11-06 S01 none (documentation) README, Doxygen, wiki in en, da and ms, final checks
@startgantt
Project starts 2026-10-28
[Baseline] starts 2026-10-28 and ends 2026-10-28
[Scaffold] starts 2026-10-28 and ends 2026-10-29
[Steps 1 and 2] starts 2026-10-29 and ends 2026-10-30
[Steps 3 and 4] starts 2026-10-30 and ends 2026-10-31
[Steps 5 and 6] starts 2026-10-31 and ends 2026-11-01
[Steps 7 and 8] starts 2026-11-01 and ends 2026-11-02
[Step 9] starts 2026-11-02 and ends 2026-11-04
[Documentation] starts 2026-11-04 and ends 2026-11-06
[Baseline Go/No-Go] happens 2026-10-28
[Scaffold Go/No-Go] happens 2026-10-29
[Steps 1 and 2 Go/No-Go] happens 2026-10-30
[Steps 3 and 4 Go/No-Go] happens 2026-10-31
[Steps 5 and 6 Go/No-Go] happens 2026-11-01
[Steps 7 and 8 Go/No-Go] happens 2026-11-02
[Step 9 Go/No-Go] happens 2026-11-04
[Release Go/No-Go] happens 2026-11-06
@endgantt

Scope Coverage

Business Case scope item Gateway
Selenium bot for the practice site, with the assignment's function names MIL-003, MIL-004, MIL-006, MIL-007
Lecture steps 1 to 9 MIL-003 (1, 2), MIL-004 (3, 4), MIL-005 (5, 6), MIL-006 (7, 8), MIL-007 (9)
Python project files: src/, tests/, docs/, pyproject.toml, constants.py, .gitignore, Doxyfile, README MIL-002, MIL-008
Unit tests with pytest MIL-002 to MIL-007
One screenshot per lecture step in README and wiki MIL-003 to MIL-007 (capture), MIL-008 (use)
Wiki in en, da and ms MIL-008
Repository description and topics MIL-001

Dependencies

MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006 → MIL-007 → MIL-008

A No-Go on a gateway stops all later gateways until it is fixed and re-reviewed. The end date then moves by the days spent on the rework; S01 decides a move of the end date.

Plan Risks

Risk Impact Mitigation
The practice site changes its page structure (Business Case risk: site changes) Steps 3 to 9 need rework Selectors only in constants.py; the first task of MIL-003 records the page as seen
The container starts with an empty site database (state lives in the browser profile) Login and booking cannot be shown MIL-003 registers a documented test account in a profile volume; browser runs reset data through the admin page
Stand-in review misses a defect Defect reaches main RC-* marks the review as not independent; S01 reviews the final summary
Translations take longer than planned MIL-008 slips Write English first; da and ms follow page by page; no extra pages

Open Issues

  • Target repository: the user names https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code, but origin is Tirsvad-Udemy-100-days-of-code/049-snack-and-lift. The plan uses origin (description and topics are set there) until S01 states otherwise in chat.
  • The Business Case sets no deadline; the window 2026-10-28 to 2026-11-06 is this plan's own assumption.
  • No QC checklist exists for accepting the Project Plan beyond QC-PP-001; S01's acceptance of the plan in chat accepts the row.