Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004, US-001
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-13 Accepted Jens Tirsvad Nielsen S01 Initial version f1b3c03
2026-10-13 Proposed Jens Tirsvad Nielsen AI as stand-in for S01 CrossReference: added US-001 pending

Purpose

This plan schedules the four phases that deliver the squirrel census assignment: tooling, analysis, documentation and wiki publication. It schedules them against the Business Case constraint of one pull request per milestone and a single-day effort.

Planning Assumptions

  • Week 1 starts 2026-10-13 (the day of the plan); the plan ends by 2026-10-16.
  • Phase length: one day per phase.
  • One branch and one pull request per milestone, each closing the issues of its tasks (BC-001 Constraints).
  • The Product Owner and reviewer is S01 for every phase (SA-001); in autonomous mode the AI acts as stand-in and records it in each review record.
  • The plan is accepted by S01 in chat; the Project Plan has no quality control (QC) checklist.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
G1 Project scaffold and tooling MIL-001 2026-10-13 to 2026-10-14 2026-10-14 S01 none .gitignore, pyproject.toml, constants, Doxyfile, continuous integration (CI), repository metadata Milestone 124
G2 Squirrel census analysis MIL-002 2026-10-14 to 2026-10-15 2026-10-15 S01 US-001 Package, tests, census file, squirrel_count.csv Milestone 125
G3 README, source documentation and screenshots MIL-003 2026-10-15 to 2026-10-16 2026-10-16 S01 none README, Doxygen comments, screenshots Milestone 126
G4 Wiki and publication MIL-004 2026-10-16 2026-10-16 S01 none Wiki in en, da and ms Milestone 127
@startgantt
Project starts 2026-10-13
[G1 Project scaffold] starts 2026-10-13 and ends 2026-10-14
[G2 Census analysis] starts 2026-10-14 and ends 2026-10-15
[G3 Documentation] starts 2026-10-15 and ends 2026-10-16
[G4 Wiki] starts 2026-10-16 and ends 2026-10-16
[G1 Go/No-Go] happens 2026-10-14
[G2 Go/No-Go] happens 2026-10-15
[G3 Go/No-Go] happens 2026-10-16
[G4 Go/No-Go] happens 2026-10-16
@endgantt

Scope Coverage

Business Case scope item Gateway
Reading the census file and counting by primary fur colour G2
Summary table exported as squirrel_count.csv G2
Command line entry point, constants.py, pyproject.toml, .gitignore, tests, CI G1 and G2
Doxygen comments, Doxyfile, build instructions G1 and G3
README, screenshots G3
Three-language wiki G4
Repository description and topics G1 (set) and G4 (verified)

Dependencies

G1 -> G2 -> G3 -> G4

A No-Go at a gateway stops the later gateways; their dates move by the days the rework takes.

Plan Risks

Risk Impact Mitigation
CI runner is not available on the git host The CI workflow cannot be shown green Run the same commands locally and report the missing runner
Wiki repository cannot be pushed G4 deliverable is not published Keep the pages under docs/wiki/ and report it
Doxygen is not installed locally The documentation build cannot be verified Report as not verified; document the command

Open Issues

  • The repository URL in the request (Tirsvad-Udemy-100_days_of_code) differs from origin (Tirsvad-Udemy-100-days-of-code/025-squirrel); the plan follows origin.
  • The census file (730 kilobytes) is assumed to be committed under data/; S01 can veto this at plan acceptance.
  • The lecture uses Pandas; the plan uses the standard library to keep zero runtime dependencies (ADR-0001, SA-001 conflict list).