Project Plan: Turtle Challenges

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-07 Proposed Jens Tirsvad Nielsen S01 Initial version 4b3391b

Purpose

This plan schedules the four milestones that deliver the Turtle Challenges repository, one milestone per pull request, so that the work is complete by 2026-10-21, the end date in the constraints of BC-001. Each milestone is one MIL-* document with its own tasks; the tasks become issues on the git host.

Planning Assumptions

  • Week 1 starts 2026-10-07; the plan ends by 2026-10-21, per the Business Case constraint.
  • Milestone length: three to four days, the length of one small pull request.
  • S01 is the owner and the approving reviewer of every milestone (see SA-001); communication with S01 follows the cadence of the Stakeholder Analysis: at every milestone.
  • The milestone dates are proposals; S01 confirms or moves them when reviewing this plan.
  • One branch per milestone, named after it (mil-001-project-foundation and so on), opened as one pull request that closes its issues.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Project Foundation MIL-001 2026-10-07 to 2026-10-10 2026-10-10 S01 none pyproject.toml, .gitignore, package and test skeleton, Doxyfile, continuous integration, README, repository description and topics
Square and Dashed Line MIL-002 2026-10-11 to 2026-10-14 2026-10-14 S01 none Pen protocol, draw_square, draw_dashed_line, fake turtle, tests, command line entry
Shapes and Random Color MIL-003 2026-10-15 to 2026-10-17 2026-10-17 S01 none random_color, color palette, draw_shape, draw_shapes, tests
Random Walk and Spirograph MIL-004 2026-10-18 to 2026-10-21 2026-10-21 S01 none random_walk, draw_spirograph, tests, final README
@startgantt
Project starts 2026-10-07
[Project Foundation] starts 2026-10-07 and ends 2026-10-10
[Square and Dashed Line] starts 2026-10-11 and ends 2026-10-14
[Shapes and Random Color] starts 2026-10-15 and ends 2026-10-17
[Random Walk and Spirograph] starts 2026-10-18 and ends 2026-10-21
[Project Foundation Go/No-Go] happens 2026-10-10
[Square and Dashed Line Go/No-Go] happens 2026-10-14
[Shapes and Random Color Go/No-Go] happens 2026-10-17
[Random Walk and Spirograph Go/No-Go] happens 2026-10-21
@endgantt

Scope Coverage

Business Case scope item Gateway
src/, tests/, docs/ structure, constants.py, pyproject.toml MIL-001
Python .gitignore MIL-001
pytest, ruff and mypy set-up MIL-001; each later milestone adds its tests
Continuous integration workflow MIL-001
Doxyfile and the command to build the documentation MIL-001; each later milestone keeps 0 warnings
README with set-up for Windows PowerShell, Linux Debian and macOS MIL-001 (first version), MIL-004 (final)
Description and topics on the Gitea host and on GitHub MIL-001
Challenge 1, draw a square MIL-002
Challenge 2, draw a dashed line MIL-002
Challenge 3, draw different shapes, and the random_color helper MIL-003
Challenge 4, generate a random walk MIL-004
Challenge 5, draw a spirograph MIL-004

Dependencies

MIL-001 → MIL-002 → MIL-003 → MIL-004

Each milestone needs the previous one Accepted with a Go review. A No-Go returns the milestone for rework and every later window moves by the rework time; the end date 2026-10-21 has no slack beyond the windows, so a No-Go on any milestone means S01 re-plans the remaining dates instead of letting them slide unrecorded.

Plan Risks

Risk Impact Mitigation
A milestone slips and the end date 2026-10-21 is missed The deadline in BC-001 is missed Milestones are small; a No-Go triggers a re-plan with S01 and a new row in this document's Version History
The Pen protocol of MIL-002 is wrong, and MIL-003 and MIL-004 build on it Rework spreads over three milestones Criteria 1, 2 and 5 of MIL-002 test the protocol with the fake turtle before anything depends on it
The Gitea host has no Actions runner Continuous integration cannot confirm the checks Every milestone records the local results of pytest, ruff, mypy and Doxygen in its review; see the open issue below
A token in .env expires or lacks a scope Issues or repository metadata cannot be created S01 renews the token; the dry run of sync-project.sh shows the plan without a token

Open Issues

  • Python bound: "Python greater than 3.13" is read as >=3.13 (3.13.14 is installed on S01's machine). If a version newer than 3.13 is meant, requires-python and the continuous integration version change to 3.14 or later, which is not installed.
  • Dashed line length: Turtle Challenge 2 says "a total of 50 segments", while the lecture's loop runs 15 times. The plan uses 50 dashes as a constant (DASH_COUNT) in constants.py; S01 confirms or sets 15.
  • README template: the agreed README template (Requirements, Set up, Run, Run the tests, Continuous integration, Build the source documentation, Project layout, License) differs from framework/templates/README-template.md. framework/scripts/check-readme.sh would flag the difference if its opt-in check were enabled; the agreed template is followed. S01 decides whether the framework check stays off.
  • Use cases and user stories: every task is a plain technical task. The program has one actor and one action (run a challenge), so no UC or US is written. S01 confirms.
  • Development tools: ruff and mypy are added as development dependencies, beyond the pytest the brief names, because QC-PY-001 requires a formatter, a linter and (optionally) a strict type check. They are not runtime dependencies.
  • Continuous integration host: the workflow lives in .github/workflows/ci.yml, which GitHub Actions and Gitea Actions both read. Whether the Gitea host has a runner is not known.
  • Diagram: the PlantUML Gantt chart is not rendered yet because no PlantUML server is configured (render-diagrams.sh --server <url>).
  • Reviews: BC-001, SA-001, DICT-001 and the four milestones were reviewed and ended in Go on 2026-10-07 (RC-007 to RC-013, which re-review RC-001 to RC-006); their Version History rows are Accepted. S01 accepted, in chat, that the author is also the reviewer, because the project has one person and no governance document exists. This plan has no checklist, so S01 accepts it directly: its row is still Proposed. S01 waived the plan-first gate in chat on 2026-10-07 for the first build, so the code of all four milestones was written before any document was reviewed; the waiver does not carry over to the next request. The code has not been reviewed against QC-PY-001 yet.
  • GitHub: issues are synced to the origin remote (the Gitea host) only; the GitHub mirror gets the description and topics but no milestones or issues.