S01 accepted the assistant's runs as the measure for success criteria 1 and 5 and
recorded Go on the re-check of the Business Case success criteria on main. All seven
criteria are met, and the conditions of RC-018 are closed. The traceability matrix
row follows the verdict.
Refs #28
S01 decided the check of the Business Case success criteria on 2026-10-08. Six of the
seven criteria are met; criterion 5 is not met until the code is on main and on
GitHub, so the first three action items of RC-018 are the conditions. The
traceability matrix row follows the verdict.
Refs #28
A new row for the check of the success criteria of BC-001 against the delivered
repository, for the gate of MIL-004. Its record RC-018 is a draft with the verdict
Pending, so the row says draft, no verdict.
Refs #28
RC-014 to RC-017 review the Python code each milestone added or changed and all
four end in Go. S01 accepted the imports inside create_window and create_pen as a
documented exception, the name tim, N-A for criterion 10 (the project has no
design class diagram) and the lower-bounded development tools. The traceability
matrix lists the code of each milestone.
Closes#8Closes#15Closes#22Closes#29
Business case BC-001, stakeholder analysis SA-001, project plan PP-001, the four
milestones MIL-001 to MIL-004, the domain dictionary DICT-001, the review records
RC-001 to RC-013 and the traceability matrix.
The reviews end in Go: the business case, stakeholder analysis, dictionary and the
four milestones are Accepted. The project plan is still Proposed; it has no
checklist and is accepted directly by the Product Owner.