Commit Graph
5 Commits
Author SHA1 Message Date
Tirsvad c893fc1a17 Update the project plan Reviews wording after the code reviews
The Reviews open issue now records the code reviews of the four milestones against
QC-PY-001 (RC-014 to RC-017, all Go). S01, the Product Owner, accepted the new
version on 2026-10-08, so the Version History gets a new Accepted row and the
previous one becomes Deprecated.
2026-10-08 00:26:04 +08:00
Tirsvad 795b9dba39 Resolve pending commit links
CI / checks (pull_request) Successful in 1m1s
Replace pending in the Version History of the project plan with the link to the
commit that accepted it.
2026-10-08 00:12:24 +08:00
Tirsvad 16183ccff6 Accept the project plan and link the synced milestones
S01, the Product Owner, accepted PP-001 on 2026-10-08: the Version History gets
a new Accepted row and the Reviews open issue says so. The Gateway Schedule now
links the four milestones that were created on the Gitea host (issues #1 to #29).
2026-10-08 00:12:23 +08:00
Tirsvad 1526262910 Resolve pending commit links
Replace pending in the Version History of the documents with the link to
the commit that added them.
2026-10-07 23:58:35 +08:00
Tirsvad 4b3391b226 Add the business case, stakeholder analysis, plan, milestones, dictionary and reviews
Business case BC-001, stakeholder analysis SA-001, project plan PP-001, the four
milestones MIL-001 to MIL-004, the domain dictionary DICT-001, the review records
RC-001 to RC-013 and the traceability matrix.

The reviews end in Go: the business case, stakeholder analysis, dictionary and the
four milestones are Accepted. The project plan is still Proposed; it has no
checklist and is accepted directly by the Product Owner.
2026-10-07 23:58:31 +08:00