Tirsvad 54f60a951a Record the verdict Go-with-conditions on RC-018
S01 decided the check of the Business Case success criteria on 2026-10-08. Six of the
seven criteria are met; criterion 5 is not met until the code is on main and on
GitHub, so the first three action items of RC-018 are the conditions. The
traceability matrix row follows the verdict.

Refs #28
2026-10-08 00:41:15 +08:00
Tirsvad 665301689d Resolve pending commit links
CI / checks (pull_request) Successful in 1m2s
Replace pending in the Version History of RC-018 with the link to the commit that
added it.
2026-10-08 00:37:08 +08:00
Tirsvad 76ac50e591 Record the verification of the Business Case success criteria
RC-018 checks the seven success criteria of BC-001 against the delivered repository
with a fresh clone, the README steps under PowerShell, the real command, the host's
CI runs and settings, and the pull requests. Criteria 1 to 4, 6 and 7 are met.
Criterion 5 is not met as written yet: the README clones the GitHub repository,
which holds only the initial commit until the pull requests are merged. The proposed
verdict is Go-with-conditions and S01 decides.

Refs #28
2026-10-08 00:37:07 +08:00