# Project Plan: Hirst Painting ## Metadata | Key | Value | | --- | --- | | ID | PP-001 | | CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002] | | Language | en | | Domain | it | ## Version History | Date | Status | Author | Reviewer | Change | Commit | | --- | --- | --- | --- | --- | --- | | 2026-10-07 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending | --- ## Purpose This plan schedules the two phases of the Hirst painting project, the colour palette and the spot painting, inside the one-week limit that [BC-001] sets (2026-10-07 to 2026-10-14). Each phase is a gateway with its own milestone document, and each gateway ends with a Go/No-Go decision by S01. ## Planning Assumptions - Week 1 starts 2026-10-07; the plan ends by 2026-10-14, per the Business Case assumption confirmed by S01. - The baseline documents ([BC-001], [SA-001] and their review records) are finished on 2026-10-07, before the first phase starts. - Phase length: two to five days, because the work is one small script. The palette phase is shorter because it is the smaller of the two. - S01 owns both phases and takes both Go/No-Go decisions; S01 is the only stakeholder in [SA-001], so communication follows the review gates in that document. - No user stories exist: the program has no user interaction beyond the exit click, so the Stories column is empty. ## Gateway Schedule | Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone | | --- | --- | --- | --- | --- | --- | --- | --- | | Colour palette | [MIL-001] | 2026-10-07 to 2026-10-09 | 2026-10-09 | S01 | none | Palette function that returns the reference image's colours without white shades | [MIL-001 milestone] | | Spot painting | [MIL-002] | 2026-10-10 to 2026-10-14 | 2026-10-14 | S01 | none | Program that draws the 10 by 10 painting and meets SC1 to SC7 of [BC-001] | [MIL-002 milestone] | ```plantuml @startgantt Project starts 2026-10-07 [Colour palette] starts 2026-10-07 and ends 2026-10-09 [Colour palette Go/No-Go] happens 2026-10-09 [Spot painting] starts 2026-10-10 and ends 2026-10-14 [Spot painting Go/No-Go] happens 2026-10-14 @endgantt ``` ## Scope Coverage | Business Case scope item | Gateway | | --- | --- | | One Python program using `turtle`, `random` and `colorgram` | [MIL-001] (`colorgram` part), [MIL-002] (`turtle` and `random` part) | | Palette extracted from one reference image, white shades removed | [MIL-001] | | Drawing the 10 by 10 dot grid: size, spacing, row change, heading | [MIL-002] | | Screen handling: `exitonclick`, hidden turtle, pen up, drawing speed | [MIL-002] | | Framework documents and review records for the plan-first workflow | Finished before the first gateway ([BC-001], [SA-001], this plan, [MIL-001], [MIL-002] and their reviews); the review of each phase's code is a task in that phase | ## Dependencies ``` Baseline documents → [MIL-001] Colour palette → [MIL-002] Spot painting ``` [MIL-002] needs the palette function from [MIL-001]. A No-Go on [MIL-001] moves the start of [MIL-002] by the days needed to rework and re-review; the one-week limit then has no slack, so S01 decides whether to extend it. ## Plan Risks | Risk | Impact | Mitigation | | --- | --- | --- | | The reference image is not supplied before the palette phase starts | [MIL-001] cannot start its extraction task; the window of two to three days is lost | The tasks that do not need the image (toolchain check, white filter and its tests) come first; S01 decides on another image if this one stays unavailable | | A No-Go on the palette phase | [MIL-002] starts late and the one-week limit is missed | The palette phase is the smaller one and ends 2026-10-09, leaving five days for the painting phase | | Review effort is large compared with the code | Time goes to documents instead of the program | Two phases, plain tasks, no use cases or design artifacts, as set out in [BC-001] | | The Project Plan has no quality checklist | The plan is accepted on S01's judgement alone | S01 checks the plan against the one-week limit of [BC-001] and the Go/No-Go criteria of both milestones | ## Open Issues - **Reference image:** its location is still unknown. S01 supplies it before task 4 of [MIL-001]. - **Project Plan review:** the Project Plan has no quality checklist yet, so it is `Accepted` when S01 says so in chat (done on 2026-10-07); no review record is written for it. - **Milestone links:** `sync-project.sh --apply` ran on 2026-10-07 and created the two Milestones and issues #1 to #13 on the git host; the Milestone column links to them. --- [BC-001]: ./business-case.md [SA-001]: ./stakeholder-analysis.md [MIL-001]: ./milestones/mil-001-palette.md [MIL-002]: ./milestones/mil-002-painting.md [MIL-001 milestone]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-hirst-painting/milestone/68 [MIL-002 milestone]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-hirst-painting/milestone/69