Add milestone MIL-003 Visible Colours (due 2026-10-10): a contrast measure and a
faint-colour filter in the palette extraction, with their tests, a real run
that rechecks SC1 to SC8, and the code review. Five Go criteria and six plain
technical tasks, no use cases.
Revise PP-001: the MIL-003 gateway in the schedule and the Gantt chart, the new
scope item, the dependency on MIL-001 and MIL-002, and a plan risk. Accepted by
S01 in chat.
Record the review of MIL-003 as RC-008 (verdict Go, terms and Tasks wording
confirmed by S01).
Replace `pending` in the Version History of BC-001, SA-001, PP-001, MIL-001,
MIL-002 and RC-001 to RC-005 with links to the commits that introduced the rows.
Add the Business Case (BC-001), Stakeholder Analysis (SA-001), Project Plan
(PP-001) and two milestones: MIL-001 Colour Palette and MIL-002 Spot Painting.
Record their reviews as RC-001 to RC-004 (all Go, self-review accepted by S01).
The PO language is English and the domain is IT. The milestones and their 13
tasks are synced as Gitea milestones 68 and 69 and issues #1 to #13.