Tirsvad c6dfb5258c Resolve pending commit links
Replace `pending` in the Version History of BC-001, PP-001, MIL-003, RC-007 and
RC-008 with links to the commits that introduced the rows.
2026-10-08 00:45:33 +08:00
Tirsvad 188b2e9700 Plan the visible colours phase: MIL-003 and the Project Plan revision
Add milestone MIL-003 Visible Colours (due 2026-10-10): a contrast measure and a
faint-colour filter in the palette extraction, with their tests, a real run
that rechecks SC1 to SC8, and the code review. Five Go criteria and six plain
technical tasks, no use cases.

Revise PP-001: the MIL-003 gateway in the schedule and the Gantt chart, the new
scope item, the dependency on MIL-001 and MIL-002, and a plan risk. Accepted by
S01 in chat.

Record the review of MIL-003 as RC-008 (verdict Go, terms and Tasks wording
confirmed by S01).
2026-10-08 00:45:20 +08:00
Tirsvad e6988d5648 Resolve pending commit link
Replace `pending` in the Version History of PP-001 with a link to the commit
that introduced the row.
2026-10-08 00:27:20 +08:00
Tirsvad a6b17d30bc Record the Go decisions of MIL-001 and MIL-002 in the Project Plan
Add a Gateway Decisions section to PP-001: S01 decided Go on both gateways on
2026-10-08, ahead of the planned 2026-10-09 and 2026-10-14, because every Go
criterion was already met. Each row names the criteria, the review record
(RC-005, RC-006) and the merged pull request (#14, #16).

Close the reference-image open issue, which has been resolved since S01
supplied the image on 2026-10-07. The two open decisions on RC-006 (the display
requirement of the tests, the pale palette colours) did not block either gate.
2026-10-08 00:27:13 +08:00
Tirsvad 412237afe4 Resolve pending commit links
Replace `pending` in the Version History of BC-001, SA-001, PP-001, MIL-001,
MIL-002 and RC-001 to RC-005 with links to the commits that introduced the rows.
2026-10-07 23:49:56 +08:00
Tirsvad b823d1f405 Plan the Hirst painting project and review the plan documents
Add the Business Case (BC-001), Stakeholder Analysis (SA-001), Project Plan
(PP-001) and two milestones: MIL-001 Colour Palette and MIL-002 Spot Painting.
Record their reviews as RC-001 to RC-004 (all Go, self-review accepted by S01).

The PO language is English and the domain is IT. The milestones and their 13
tasks are synced as Gitea milestones 68 and 69 and issues #1 to #13.
2026-10-07 23:49:16 +08:00