Tirsvad 22b7329b47 Sync MIL-003 to Gitea: unique task 6 title, delta confirmation, milestone link
The MIL-003 milestone (id 74) and its issues #22 to #27 are created on Gitea.

Creating them exposed a collision: task 6 of MIL-003 had the same title as
task 6 of MIL-001, and sync-project.sh matches issues by title, so it
overwrote the closed MIL-001 issue #6 (milestone and a Phase line). Issue #6
was restored, and MIL-003 task 6 is renamed "Review the visible-colours code
against qc-programming-python", which is issue #27. No other task title is
shared between the milestone documents.

- MIL-003: rename task 6 (new Version History row, accepted by S01).
- RC-008: add the delta confirmation for the rename; no criterion result
  changes (new row, accepted by S01).
- PP-001: link the MIL-003 gateway to its Milestone (a link update, no new
  Version History row).
2026-10-08 01:29:27 +08:00
Tirsvad c6dfb5258c Resolve pending commit links
Replace `pending` in the Version History of BC-001, PP-001, MIL-003, RC-007 and
RC-008 with links to the commits that introduced the rows.
2026-10-08 00:45:33 +08:00
Tirsvad 188b2e9700 Plan the visible colours phase: MIL-003 and the Project Plan revision
Add milestone MIL-003 Visible Colours (due 2026-10-10): a contrast measure and a
faint-colour filter in the palette extraction, with their tests, a real run
that rechecks SC1 to SC8, and the code review. Five Go criteria and six plain
technical tasks, no use cases.

Revise PP-001: the MIL-003 gateway in the schedule and the Gantt chart, the new
scope item, the dependency on MIL-001 and MIL-002, and a plan risk. Accepted by
S01 in chat.

Record the review of MIL-003 as RC-008 (verdict Go, terms and Tasks wording
confirmed by S01).
2026-10-08 00:45:20 +08:00