The MIL-003 milestone (id 74) and its issues #22 to #27 are created on Gitea.
Creating them exposed a collision: task 6 of MIL-003 had the same title as
task 6 of MIL-001, and sync-project.sh matches issues by title, so it
overwrote the closed MIL-001 issue #6 (milestone and a Phase line). Issue #6
was restored, and MIL-003 task 6 is renamed "Review the visible-colours code
against qc-programming-python", which is issue #27. No other task title is
shared between the milestone documents.
- MIL-003: rename task 6 (new Version History row, accepted by S01).
- RC-008: add the delta confirmation for the rename; no criterion result
changes (new row, accepted by S01).
- PP-001: link the MIL-003 gateway to its Milestone (a link update, no new
Version History row).
Add milestone MIL-003 Visible Colours (due 2026-10-10): a contrast measure and a
faint-colour filter in the palette extraction, with their tests, a real run
that rechecks SC1 to SC8, and the code review. Five Go criteria and six plain
technical tasks, no use cases.
Revise PP-001: the MIL-003 gateway in the schedule and the Gantt chart, the new
scope item, the dependency on MIL-001 and MIL-002, and a plan risk. Accepted by
S01 in chat.
Record the review of MIL-003 as RC-008 (verdict Go, terms and Tasks wording
confirmed by S01).