Plan the visible colours phase: MIL-003 and the Project Plan revision

Add milestone MIL-003 Visible Colours (due 2026-10-10): a contrast measure and a
faint-colour filter in the palette extraction, with their tests, a real run
that rechecks SC1 to SC8, and the code review. Five Go criteria and six plain
technical tasks, no use cases.

Revise PP-001: the MIL-003 gateway in the schedule and the Gantt chart, the new
scope item, the dependency on MIL-001 and MIL-002, and a plan risk. Accepted by
S01 in chat.

Record the review of MIL-003 as RC-008 (verdict Go, terms and Tasks wording
confirmed by S01).
This commit is contained in:
2026-10-08 00:45:20 +08:00
parent 701feb1e52
commit 188b2e9700
4 changed files with 178 additions and 14 deletions
+2 -2
View File
@@ -14,8 +14,8 @@ document of a type. `Primary File` may contain a glob (e.g.
| BC | Business Case | docs/business-case.md | 002 |
| SA | Stakeholder Analysis | docs/stakeholder-analysis.md | 002 |
| PP | Project Plan | docs/project-plan.md | 002 |
| MIL | Milestone / Gateway | docs/milestones/*.md | 003 |
| RC | SQA Review Record | docs/sqa/reviews/rc-*.md | 008 |
| MIL | Milestone / Gateway | docs/milestones/*.md | 004 |
| RC | SQA Review Record | docs/sqa/reviews/rc-*.md | 009 |
## Languages