Plan project and set up Phase 1 skeleton
CI / test (push) Successful in 54s

Add the framework submodule and the accepted planning documents:
Business Case, Stakeholder Analysis, Project Plan, three milestones,
review records RC-001 to RC-006 and the traceability matrix.

Set up the project skeleton for MIL-001: pyproject.toml (Python
>=3.13, no runtime dependencies, pytest/ruff/mypy as dev extra),
 src/coffee_machine/constants.py, a constants consistency test,
 Doxyfile and a CI workflow that runs ruff, mypy and pytest.

Task: MIL-001#1
Task: MIL-001#2
Task: MIL-001#3
Task: MIL-001#4
Task: MIL-001#5
Closes #1
Closes #2
Closes #3
Closes #4
Closes #5
This commit is contained in:
2026-10-07 10:43:22 +08:00
parent 7c7c15ddf9
commit c24f41207f
22 changed files with 1362 additions and 0 deletions
+62
View File
@@ -0,0 +1,62 @@
# Review: Project Plan PP-001
## Metadata
| Key | Value |
| --- | --- |
| ID | RC-006 |
| CrossReference | [PP-001], [QC-LANG-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-07 | Accepted | Jens Tirsvad Nielsen | S01 | Review record | pending |
---
## Artifact Under Review
- Instance reviewed: [PP-001]
- Checklist used: none (PP has no QC checklist; see the first row of Checklist Results)
- Scope: full review
- Language and domain: en / it
- Language reviewer: none
## Checklist Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | Plan schedules every phase against the Business Case constraint (no QC checklist exists for PP; validated against BC-001 and the Go/No-Go criteria of each MIL) | Pass | Three phases end on or before 2026-10-16; each MIL target date equals the plan's decision date. |
| 2 | Every required PP section is present, in order | Pass | Purpose through Open Issues are present. |
| 3 | Gateway Schedule lists every MIL document | Pass | MIL-001, MIL-002, MIL-003. |
## Language and Domain Results
Checklist: [QC-LANG-001].
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | The Metadata table has a `Language` row and a `Domain` row, and neither is a placeholder | Pass | `Language | en`, `Domain | it`. |
| 2 | `Language` is a BCP 47 code and `Domain` is a value from the registry's domain list | Pass | `en` is BCP 47; `it` is in the registry's domain list. |
| 3 | The content (prose and table cells) is written in the stated language | Pass | All prose and table cells are English. |
| 4 | The register matches the one the registry gives for the artifact type | Pass | Register is IT Executive English as the registry states. |
| 5 | Domain terms are the PO terms of the domain's dictionary, with no synonyms | Pass | No dictionary (`DICT`) exists yet; terms (Menu, CoffeeMaker, MoneyMachine, drink, resource) are the assignment's own and used consistently. |
| 6 | Metadata keys, section headings, IDs and statuses are in English | Pass | Verified by reading the file. |
| 7 | No translated twin (`<name>.<language>.md`) exists beside the document | Pass | No twin file in `docs/`. |
| 8 | A change of language or domain since the previous accepted version has a Version History row and was reviewed again | N-A | First accepted version; no language change. |
| 9 | A reviewer competent in the domain, and in the language, has confirmed that the domain terms are used correctly | Pass | S01 reads English and works in the IT domain; S01 asked for this review and acceptance in chat. |
| 10 | Abbreviations are spelled out on first use, in the stated language | Pass | PO, FURPS+, CI, PP, MIL are defined by the framework; PO is spelled out in the Stakeholder Analysis. |
## Overall Verdict
Go — validated against the Business Case and the milestones; the plan is accepted by S01 as Product Owner.
## Action Items
| Action | Owner | Due |
| --- | --- | --- |
| Fill the `Milestone` column after `sync-project.sh --apply` | S01 | 2026-10-09 |
---