Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004

Version History

Date Status Author Reviewer Change Commit
2026-10-06 Deprecated Jens Tirsvad Nielsen S01 Added MIL-004 Code Review and CI 8ef00aa
2026-10-06 Accepted Jens Tirsvad Nielsen S01 Fixed phase count, dependency overlap and stale risks and open issues (RC-009 actions) 52b9725

Purpose

Schedule the four phases that take the coffee machine from empty repository to a reviewed, published project, within the one-week duration in BC-001.

Planning Assumptions

  • Week 1 starts 2026-10-05; the plan ends by 2026-10-12.
  • Phase length: two to three days; S01 reviews each phase through a pull request (see SA-001).
  • Each phase is delivered through one or more branches and pull requests.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Project Setup MIL-001 2026-10-05 to 2026-10-07 2026-10-07 S01 none Skeleton, tooling, README Milestone 40
Coffee Machine Core MIL-002 2026-10-08 to 2026-10-10 2026-10-10 S01 none Working program Milestone 41
Quality and Publication MIL-003 2026-10-11 to 2026-10-12 2026-10-12 S01 none Tests, Doxygen, published repo Milestone 42
Code Review and CI MIL-004 2026-10-07 to 2026-10-12 2026-10-12 S01 none Source review record, CI workflow Milestone 48
@startgantt
Project starts 2026-10-05
[Project Setup] starts 2026-10-05 and ends 2026-10-07
[Coffee Machine Core] starts 2026-10-08 and ends 2026-10-10
[Quality and Publication] starts 2026-10-11 and ends 2026-10-12
[MIL-001 Go/No-Go] happens 2026-10-07
[MIL-002 Go/No-Go] happens 2026-10-10
[MIL-003 Go/No-Go] happens 2026-10-12
[Code Review and CI] starts 2026-10-07 and ends 2026-10-12
[MIL-004 Go/No-Go] happens 2026-10-12
@endgantt

Scope Coverage

Business Case scope item Gateway
Console program with constants.py MIL-002
pytest tests MIL-003
pyproject.toml, .gitignore, Doxyfile, README MIL-001
Project documents Planning, before MIL-001
Repository description and topics MIL-003
Source code review record and CI workflow MIL-004

Dependencies

MIL-001 -> MIL-002 -> MIL-003 -> MIL-004

MIL-004 may start once the MIL-003 tests are merged, so their windows overlap; its decision follows the decision of MIL-003.

A No-Go moves all later dates by the same amount.

Plan Risks

Risk Impact Mitigation
The git host has no Actions runner CI cannot run Check the host first; if none, keep the workflow file and document the local commands
Doxygen not installed locally Cannot verify docs Document the install step in README

Open Issues

  • No use cases or user stories are written; tasks are plain technical tasks implementing the assignment specification. S01 can ask for a use case ("Order a drink") if wanted.