Add review record RC-012, accept the ADR with the decision stated in two sentences and update TM-001.
4.0 KiB
4.0 KiB
Traceability Matrix
Metadata
| Key | Value |
|---|---|
| ID | TM-001 |
| CrossReference | BC-001, SA-001, PP-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005, RC-001, RC-002, RC-003, RC-004, RC-005, RC-006, RC-007, RC-008, RC-009, RC-010, RC-011, RC-012, ADR-0001 |
Version History
| Date | Status | Author | Reviewer | Change | Commit |
|---|---|---|---|---|---|
| 2026-10-10 | Deprecated | Jens Tirsvad Nielsen | S01 | Added RC-011 for the MIL-005 amendment | 20361e8 |
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | Added ADR-0001 and RC-012 | pending |
Purpose
Tracks backward/forward links between artifact instances so that the Business Case's cross-artifact traceability success criterion is measurable. A row is added or updated whenever an artifact instance is created or reviewed.
Traceability Table
| Artifact Instance | Type | Upstream (Backward Link) | Downstream (Forward Link) | Last Reviewed (RC-ID) |
|---|---|---|---|---|
| SA-001 | SA | - | BC-001 | RC-004 |
| BC-001 | BC | SA-001 | PP-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005 | RC-001, RC-008 |
| PP-001 | PP | BC-001, SA-001 | MIL-001, MIL-002, MIL-003, MIL-004, MIL-005 | RC-002, RC-009 |
| MIL-001 | MIL | BC-001, PP-001 | MIL-002 | RC-003 |
| MIL-002 | MIL | BC-001, PP-001, MIL-001 | MIL-003, MIL-005 | RC-005 |
| MIL-003 | MIL | BC-001, PP-001, MIL-002 | MIL-004 | RC-006 |
| MIL-004 | MIL | BC-001, PP-001, MIL-003 | - | RC-007 |
| RC-001 | RC | BC-001 | - | - |
| RC-002 | RC | PP-001 | - | - |
| RC-003 | RC | MIL-001 | - | - |
| RC-004 | RC | SA-001 | - | - |
| RC-005 | RC | MIL-002 | - | - |
| RC-006 | RC | MIL-003 | - | - |
| MIL-005 | MIL | BC-001, PP-001, MIL-002 | - | RC-010, RC-011 |
| RC-007 | RC | MIL-004 | - | - |
| RC-008 | RC | BC-001 | - | - |
| RC-009 | RC | PP-001 | - | - |
| RC-010 | RC | MIL-005 | - | - |
| ADR-0001 | ADR | BC-001, MIL-005 | - | RC-012 |
| RC-011 | RC | MIL-005 | - | - |
| RC-012 | RC | ADR-0001 | - | - |
Coverage Notes
-in Upstream means foundational (SA-001 has no prerequisite). In Downstream it means nothing is built on the instance yet. In Last Reviewed it means noRC-*exists (review records are not themselves reviewed).- Types with no instance yet: KPI, BMC, BPMN, UCD, US, UC, SSD, DM, OC, SD, DCD, ERD, GOV, DICT. The Project Plan lists use case candidates, but the formal use cases wait for a use case diagram and user stories.
- PP-001 and TM-001 have no QC checklist; RC-002 validated PP-001 against its Business Case constraints and the milestone Go / No-Go criteria. TM-001 has no review record.
- All review records are
Acceptedafter S01 stood in for S05 on 2026-10-10. The author and S01 are the same person, so an independent review by S05 is still open (see RC-001).