| 1 |
A concrete deliverable is defined for every gate |
Pass |
The deliverable now also names scripts as files fetched at a pinnable reference. |
| 2 |
Explicit Go/No-Go criteria are stated for each gate |
Pass |
New criterion 5 is checkable: the count of embedded scripts is 0 and a run in another organization passes. |
| 3 |
Dependencies on other milestones are explicitly mapped |
Pass |
Unchanged (MIL-003); task 6 needs no other milestone, because the checkout of a script repository was verified on 2026-10-10. |
| 4 |
Each milestone is traceable to a Business Case objective or KPI |
Pass |
Finding fixed during this review: task 6 serves O2 (one canonical copy and a defined way to reach consuming repositories) and the Traceability table listed only O4. It now lists O2 and O4. |
| 5 |
Milestone owner and approving reviewer are identified |
Pass |
Unchanged: owner S05, approving reviewer S01. |
| 6 |
Milestone has a defined target date consistent with project constraints |
Pass |
2026-11-28, confirmed (RC-029). |