Review Record: PP-001 Project Plan (PAT_FOR_GITHUB, open issues)

Metadata

Key Value
ID RC-015
CrossReference PP-001, BC-001

Version History

Date Status Author Reviewer Change Commit
2026-10-10 Accepted Jens Tirsvad Nielsen S01 Initial version b282e10

Artifact Under Review

  • Instance reviewed: PP-001
  • Checklist used: none: the Project Plan has no QC checklist. Validated against the Business Case BC-001 and the Go / No-Go criteria of each listed milestone, as PP.md prescribes.

Checklist Results

# Criterion Status Evidence/Notes
1 Every milestone in the plan has a MIL-* document and the plan's dates equal that document's target date Pass MIL-001 to MIL-005 exist; decision dates equal each Target Date.
2 Every Business Case scope item is covered by a gateway Pass Unchanged; Scope Coverage maps all items.
3 The schedule respects the Business Case constraints Pass The Business Case sets no deadline; dates are marked as proposals.
4 Dependencies between milestones are stated Pass Unchanged.
5 Every gateway has an owner who is a stakeholder ID Pass All five gateways are owned by S05.
6 Plan content is internally consistent Pass Finding fixed during this review: UC candidate 2 still listed "malformed JSON" as a credential failure although no secret is JSON any more. It now lists the empty value, a wrong or expired token (HTTP 401) and a missing permission. The secret names match the code and the guides.
7 Open Issues are current Pass Finding fixed during this review: the MIL-001 task 1 and task 3 decisions were made and are recorded in MIL-001, so they are removed. The remaining items are still open: confirm dates, no QC checklist for the Project Plan, formal use cases wait for a diagram and user stories. This closes the RC-009 action item.

Overall Verdict

Go - all seven criteria pass; the two findings were fixed during the review. S01 gave the Go in chat on 2026-10-10, standing in for the other reviewers as ADR-0002 records; there is no independent reader.

Action Items

Action Owner Due
Confirm the proposed dates and the start week (already in Open Issues) S01 2026-10-17