Review Record: MIL-007 (amendment)

Metadata

Key Value
ID RC-055
CrossReference MIL-007, QC-MIL-001

Version History

Date Status Author Reviewer Change Commit
2026-10-11 Accepted Jens Tirsvad Nielsen S01 Initial version faf13b2

Artifact Under Review

  • Instance reviewed: MIL-007 after the amendments since RC-052: current tool versions only (.NET SDK 10 or later), the results of runs 692 and 699, and the contract of ADR-0008
  • Checklist used: QC-MIL-001

Checklist Results

# Criterion Status Evidence/Notes
1 A concrete deliverable is defined for every gate Pass Unchanged, and the deliverable now states the version requirement: current tools only, .NET SDK 10 or later.
2 Explicit Go/No-Go criteria are stated for each gate Pass Finding fixed during this review: criterion 1 was amended but task 3 still carried the options of the draft (cppcheck conditional, one workflow or two). Task 3 now states the decided contract and points to ADR-0008, so criterion 2 is checkable as it stands: the ADR is accepted.
3 Dependencies on other milestones are explicitly mapped Pass Unchanged: MIL-003 and MIL-004, both closed.
4 Each milestone is traceable to a Business Case objective or KPI Pass O4, US-001.09 and .10, and now the stories US-001.16 and .17 of task 1; ADR-0008 is in CrossReference.
5 Milestone owner and approving reviewer are identified Pass Owner S05, approving reviewer S01.
6 Milestone has a defined target date consistent with project constraints Pass 2027-01-16, unchanged and confirmed on 2026-10-11.

Overall Verdict

Go - all six criteria pass; the one finding (criterion 2) was fixed during the review, together with two stale phrases (the verification results still offered a build of cppcheck, and tasks 4 and 5 said "as the ADR decides"). It restores the status Accepted of MIL-007, which the publishing action and the plan-first gate require, and it does not accept UC-005 and US-001.16 and .17 (task 1, #95), which still need their own review. S01 gave the Go in chat on 2026-10-11, standing in for the other reviewers as ADR-0002 records; there is no independent reader.

Action Items

Action Owner Due
Review and accept the extension of UC-005 and the stories US-001.16 and US-001.17 (#95) S01 before #98 and #99