| 1 |
Every milestone in the plan has a MIL-* document and the plan's dates equal that document's target date |
Pass |
MIL-001 to MIL-005 exist; decision dates equal each Target Date. |
| 2 |
Every Business Case scope item is covered by a gateway |
Pass |
Unchanged; Scope Coverage maps all items. |
| 3 |
The schedule respects the Business Case constraints |
Pass |
The Business Case sets no deadline; dates are marked as proposals. |
| 4 |
Dependencies between milestones are stated |
Pass |
Unchanged. |
| 5 |
Every gateway has an owner who is a stakeholder ID |
Pass |
All five gateways are owned by S05. |
| 6 |
Plan content is internally consistent |
Pass |
Finding fixed during this review: UC candidate 2 still listed "malformed JSON" as a credential failure although no secret is JSON any more. It now lists the empty value, a wrong or expired token (HTTP 401) and a missing permission. The secret names match the code and the guides. |
| 7 |
Open Issues are current |
Pass |
Finding fixed during this review: the MIL-001 task 1 and task 3 decisions were made and are recorded in MIL-001, so they are removed. The remaining items are still open: confirm dates, no QC checklist for the Project Plan, formal use cases wait for a diagram and user stories. This closes the RC-009 action item. |