| 1 |
Every milestone in the plan has a MIL-* document and the plan's dates equal that document's target date |
Pass |
MIL-001 to MIL-005 exist; the MIL-005 decision date 2026-12-12 equals its Target Date. |
| 2 |
Every Business Case scope item is covered by a gateway |
Pass |
The new scope item (wiki in three languages) maps to MIL-005 in Scope Coverage. |
| 3 |
The schedule respects the Business Case constraints |
Pass |
The Business Case sets no deadline. MIL-005 is scheduled after MIL-004 although it only depends on MIL-002. |
| 4 |
Dependencies between milestones are stated |
Pass |
The Dependencies diagram adds MIL-002 to MIL-005. |
| 5 |
Every gateway has an owner who is a stakeholder ID |
Pass |
MIL-005 is owned by S05. |
| 6 |
Plan content is internally consistent |
Pass |
Finding fixed during this review: Planning Assumptions still said the last decision is 2026-11-28; it now says 2026-12-12. The purpose text says five milestones. |
| 7 |
Open Issues are current |
Fail |
Open Issues still lists the answered MIL-001 task 1 and task 3 decisions (carried over from RC-002). |