Review Record: MIL-005 Wiki and translations

Metadata

Key Value
ID RC-010
CrossReference MIL-005, QC-MIL-001

Version History

Date Status Author Reviewer Change Commit
2026-10-10 Accepted Jens Tirsvad Nielsen S01 Initial version ae4e257

Artifact Under Review

Checklist Results

# Criterion Status Evidence/Notes
1 A concrete deliverable is defined for every gate Pass Fifteen wiki pages, a generation script and the AGENTS.md rule.
2 Explicit Go/No-Go criteria are stated for each gate Pass Five criteria, each with a checkable Go and No-Go column.
3 Dependencies on other milestones are explicitly mapped Pass Depends on MIL-002, with the reason.
4 Each milestone is traceable to a Business Case objective or KPI Pass Traceability maps MIL-005 to O3 of BC-001.
5 Milestone owner and approving reviewer are identified Pass Owner S05, approving reviewer S01.
6 Milestone has a defined target date consistent with project constraints Pass 2026-12-12, marked proposed; the Business Case sets no deadline.

Overall Verdict

Go - all six criteria pass. S01 gave the Go in chat on 2026-10-10. Accepting the milestone is what unlocks its tasks under the plan-first gate; the issues are still to be created with sync-project.sh --apply. The author and S01 are the same person, so the independent S05 review recorded in RC-001 is still open.

Action Items

Action Owner Due
Decide how the agent publishes to the wiki repository (task 2): push with a token or prepare changes for review S01 2026-10-17
Confirm the proposed target date with S01 and S05 S05 2026-10-17