Review Record: PP-001 Project Plan (MIL-005)

Metadata

Key Value
ID RC-009
CrossReference PP-001, BC-001

Version History

Date Status Author Reviewer Change Commit
2026-10-10 Accepted Jens Tirsvad Nielsen S01 Initial version ae4e257

Artifact Under Review

  • Instance reviewed: PP-001
  • Checklist used: none: the Project Plan has no QC checklist. Validated against the Business Case BC-001 and the Go / No-Go criteria of each listed milestone, as PP.md prescribes.

Checklist Results

# Criterion Status Evidence/Notes
1 Every milestone in the plan has a MIL-* document and the plan's dates equal that document's target date Pass MIL-001 to MIL-005 exist; the MIL-005 decision date 2026-12-12 equals its Target Date.
2 Every Business Case scope item is covered by a gateway Pass The new scope item (wiki in three languages) maps to MIL-005 in Scope Coverage.
3 The schedule respects the Business Case constraints Pass The Business Case sets no deadline. MIL-005 is scheduled after MIL-004 although it only depends on MIL-002.
4 Dependencies between milestones are stated Pass The Dependencies diagram adds MIL-002 to MIL-005.
5 Every gateway has an owner who is a stakeholder ID Pass MIL-005 is owned by S05.
6 Plan content is internally consistent Pass Finding fixed during this review: Planning Assumptions still said the last decision is 2026-11-28; it now says 2026-12-12. The purpose text says five milestones.
7 Open Issues are current Fail Open Issues still lists the answered MIL-001 task 1 and task 3 decisions (carried over from RC-002).

Overall Verdict

Go - S01 gave the Go in chat on 2026-10-10 for the revision that adds MIL-005. The open-issues finding is carried over from RC-002 and does not affect MIL-005. The author and S01 are the same person, so the independent S05 review recorded in RC-001 is still open.

Action Items

Action Owner Due
Remove the answered MIL-001 task 1 and task 3 items from Open Issues in PP-001, with a Version History row S01 2026-10-17