# Review Record: MIL-009 outcome ## Metadata | Key | Value | | --- | --- | | ID | RC-066 | | CrossReference | [MIL-009], [QC-MIL-001], [RC-064], [ADR-0004] | ## Version History | Date | Status | Author | Reviewer | Change | Commit | | --- | --- | --- | --- | --- | --- | | 2026-10-14 | Accepted | Jens Tirsvad Nielsen | AI as stand-in for S01 | Initial version | pending | --- ## Artifact Under Review - Instance reviewed: [MIL-009] after the verification results were recorded on 2026-10-14 - Checklist used: [QC-MIL-001] - Scope: delta re-review of the Go / No-Go outcome; the earlier record is [RC-064] - Language and domain: n/a (technical type) - Mode: autonomous, not independent (the reviewer is `AI as stand-in for S01`; the user accepted the plan in chat on 2026-10-14) ## Checklist Results | # | Criterion | Status | Evidence/Notes | | --- | --- | --- | --- | | 1 | A concrete deliverable is defined for every gate | Pass | Delivered: framework 0.7.0, seven callers, removals, ADR-0004 superseded, 2.0.0. | | 2 | Explicit Go/No-Go criteria are stated for each gate | Pass | All seven criteria have a recorded result, each with evidence. | | 3 | Dependencies on other milestones are explicitly mapped | Pass | MIL-008 and the framework release were met first. | | 4 | Each milestone is traceable to a Business Case objective or KPI | Pass | O2, O3, unchanged. | | 5 | Milestone owner and approving reviewer are identified | Pass | S05 and S01. | | 6 | Milestone has a defined target date consistent with project constraints | Pass | Target 2026-11-30; the gate was met on 2026-10-14. | ## Overall Verdict Go - the gate is met: all seven criteria are Go (criterion 5 with a recorded note that the marker text remains in history records and the upgrade note). The AI records the outcome as stand-in for S01; there is no independent reader, and the decision stays open to challenge in the run summary. ## Action Items | Action | Owner | Due | | --- | --- | --- | | Fix the two failing tests of `repo-foundry` on `main` (the checklist layout of its test fixture); not part of this milestone | S05 | not planned | | Move the `framework` pin of `github-action` itself from `v0.6.2` to `v0.7.0` | S05 | not planned | --- [MIL-009]: ../../milestones/mil-009-migrate-wiki-callers-and-remove-scoped-workflow.md [QC-MIL-001]: ../../../framework/qc/artifacts/qc-milestones-gateways.md [RC-064]: ./rc-064-mil-009-plan.md [ADR-0004]: ../../adr/adr-0004-shared-wiki-publishing-opt-in.md