Approve the token permissions and confirm the target dates

S01, standing in for S05 (ADR-0002), approves the minimum Gitea and GitHub
token permissions, recorded with the evidence from the Gitea source and the
GitHub documentation; they are still not tested with a minimal token on the
instance. Confirm the target dates of MIL-001 to MIL-006 and PP-001 (RC-026
to RC-032), update TM-001 and regenerate the Credentials wiki page with its
translations.

Task: MIL-002#4
This commit is contained in:
2026-10-10 13:23:40 +08:00
parent 5608630d3d
commit ea06eaaa69
20 changed files with 469 additions and 69 deletions
+6 -7
View File
@@ -4,13 +4,13 @@
| Key | Value |
| --- | --- |
| ID | PP-001 |
| CrossReference | [BC-001], [SA-001], [US-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004], [MIL-005], [MIL-006] |
| CrossReference | [BC-001], [SA-001], [ADR-0002], [US-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004], [MIL-005], [MIL-006] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-10 | Deprecated | Jens Tirsvad Nielsen | S01 | Added gateway MIL-006 (shared wiki publishing) | [6b8e36d] |
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | P1 use cases written and accepted (UCD-001, US-001, UC-001 to UC-004): Open Issues updated | [a2bf2d4] |
| 2026-10-10 | Deprecated | Jens Tirsvad Nielsen | S01 | P1 use cases written and accepted (UCD-001, US-001, UC-001 to UC-004): Open Issues updated | [a2bf2d4] |
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | Dates confirmed by S01 (stand-in for S05); the confirmation item is removed from Open Issues | pending |
---
@@ -18,13 +18,13 @@
This plan schedules six milestones that move the repository from one
workflow with known defects to a documented, versioned collection of shared
workflows. The Business Case sets no deadline, so the dates are proposals.
workflows. The Business Case sets no deadline, so the dates are the plan's own; they were confirmed on 2026-10-10 by S01, standing in for S05 (ADR-0002).
## Planning Assumptions
- Week 1 starts 2026-10-05; phases are two weeks long; the last decision is 2026-12-26.
- Work on a milestone starts only after its `MIL-*` document is `Accepted`.
- Dates are proposed by the author and need confirmation by S01 and S05.
- Dates were confirmed on 2026-10-10 by S01, standing in for S05 (ADR-0002).
## Gateway Schedule
@@ -84,7 +84,6 @@ A No-Go moves every later window by the rework time of the failed milestone.
## Open Issues
- Confirm the proposed dates and the start week (S01 and S05).
- No QC checklist exists for the Project Plan.
- The P1 candidates are written as brief use cases (UC-001 to UC-004) with a use case diagram (UCD-001) and user stories (US-001). The P2 and P3 candidates have no use case document yet.
@@ -245,6 +244,7 @@ no tests, no release process.
[BC-001]: ./business-case.md
[SA-001]: ./stakeholder-analysis.md
[US-001]: ./user-stories.md
[ADR-0002]: ./adr/adr-0002-s01-approves-as-stand-in.md
[MIL-001]: ./milestones/mil-001-stabilise-metadata-sync.md
[MIL-002]: ./milestones/mil-002-onboarding-and-operations.md
[MIL-003]: ./milestones/mil-003-quality-checks.md
@@ -257,5 +257,4 @@ no tests, no release process.
[Milestone MIL-004]: https://git.tirsystem.com/TirSystem/github-action/milestone/21
[Milestone MIL-005]: https://git.tirsystem.com/TirSystem/github-action/milestone/93
[Milestone MIL-006]: https://git.tirsystem.com/TirSystem/github-action/milestone/94
[6b8e36d]: https://git.tirsystem.com/TirSystem/github-action/commit/6b8e36d67ac9af165b180bc0045289e41cfd1fc3
[a2bf2d4]: https://git.tirsystem.com/TirSystem/github-action/commit/a2bf2d420416f7aff2badc6fe32a7690e2e523fd