Approve the token permissions and confirm the target dates

S01, standing in for S05 (ADR-0002), approves the minimum Gitea and GitHub
token permissions, recorded with the evidence from the Gitea source and the
GitHub documentation; they are still not tested with a minimal token on the
instance. Confirm the target dates of MIL-001 to MIL-006 and PP-001 (RC-026
to RC-032), update TM-001 and regenerate the Credentials wiki page with its
translations.

Task: MIL-002#4
This commit is contained in:
2026-10-10 13:23:40 +08:00
parent 5608630d3d
commit ea06eaaa69
20 changed files with 469 additions and 69 deletions
@@ -4,12 +4,13 @@
| Key | Value |
| --- | --- |
| ID | MIL-006 |
| CrossReference | [BC-001], [MIL-005], [ADR-0003] |
| CrossReference | [BC-001], [MIL-005], [ADR-0003], [ADR-0002] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | [6b8e36d] |
| 2026-10-10 | Deprecated | Jens Tirsvad Nielsen | S01 | Initial version | [6b8e36d] |
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | Target date 2026-12-26 confirmed on 2026-10-10 by S01 (stand-in for S05) | pending |
---
@@ -59,7 +60,7 @@ repository other than this one that publishes its wiki through it.
## Target Date
2026-12-26 — proposed; to be confirmed by S01 and S05 (the Business Case sets no deadline).
2026-12-26 — confirmed on 2026-10-10 by S01, standing in for S05 (ADR-0002); the Business Case sets no deadline.
## Tasks
@@ -75,3 +76,4 @@ repository other than this one that publishes its wiki through it.
[BC-001]: ../business-case.md
[6b8e36d]: https://git.tirsystem.com/TirSystem/github-action/commit/6b8e36d67ac9af165b180bc0045289e41cfd1fc3
[ADR-0002]: ../adr/adr-0002-s01-approves-as-stand-in.md