# Review Record: MIL-007
|
||||
|
||||
## Metadata
|
||||
| Key | Value |
|
||||
| --- | --- |
|
||||
| ID | RC-052 |
|
||||
| CrossReference | [MIL-007], [QC-MIL-001] |
|
||||
|
||||
## Version History
|
||||
| Date | Status | Author | Reviewer | Change | Commit |
|
||||
| --- | --- | --- | --- | --- | --- |
|
||||
| 2026-10-11 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending |
|
||||
|
||||
---
|
||||
|
||||
## Artifact Under Review
|
||||
|
||||
- Instance reviewed: [MIL-007]
|
||||
- Checklist used: [QC-MIL-001]
|
||||
|
||||
## Checklist Results
|
||||
|
||||
| # | Criterion | Status | Evidence/Notes |
|
||||
| --- | --- | --- | --- |
|
||||
| 1 | A concrete deliverable is defined for every gate | Pass | Two reusable workflows with pinned tools, guides and wiki pages in three languages, a use in another repository and a release. |
|
||||
| 2 | Explicit Go/No-Go criteria are stated for each gate | Pass | Six criteria, each with a Go and a No-Go: runner verified, ADR accepted, seeded failure visible, a run in another repository, no embedded script, released. |
|
||||
| 3 | Dependencies on other milestones are explicitly mapped | Pass | MIL-003 for the contract and mechanism, MIL-004 for the release; both are closed. |
|
||||
| 4 | Each milestone is traceable to a Business Case objective or KPI | Pass | O4, and US-001.09 and US-001.10 which the milestone extends. |
|
||||
| 5 | Milestone owner and approving reviewer are identified | Pass | Owner S05, approving reviewer S01. |
|
||||
| 6 | Milestone has a defined target date consistent with project constraints | Pass | 2027-01-16, after the last decision of the plan; the Business Case sets no deadline. |
|
||||
|
||||
## Overall Verdict
|
||||
|
||||
Go - all six criteria pass; no findings. The plan-first order holds inside the milestone: the use case and stories (task 1), the runner check (task 2) and the contract ADR (task 3) come before any workflow (tasks 4 and 5). The decision between one workflow and one per language is left to the ADR and is not made here. S01 gave the Go in chat on 2026-10-11, standing in for the other reviewers as ADR-0002 records; there is no independent reader.
|
||||
|
||||
## Action Items
|
||||
|
||||
| Action | Owner | Due |
|
||||
| --- | --- | --- |
|
||||
| Run `sync-project.sh --apply` so that the milestone and its issues exist | S05 | 2026-10-11 |
|
||||
| Decide in the ADR (task 3) one workflow or one per language, and whether C is included | S01 | before tasks 4 and 5 |
|
||||
|
||||
---
|
||||
|
||||
[MIL-007]: ../../milestones/mil-007-cpp-csharp-quality-checks.md
|
||||
[QC-MIL-001]: ../../../framework/qc/qc-milestones-gateways.md
|
||||