Review and accept MIL-007 and the PP-001 amendment
This commit is contained in:
@@ -10,7 +10,7 @@
|
||||
| Date | Status | Author | Reviewer | Change | Commit |
|
||||
| --- | --- | --- | --- | --- | --- |
|
||||
| 2026-10-10 | Deprecated | Jens Tirsvad Nielsen | S01 | Dates confirmed by S01 (stand-in for S05); the confirmation item is removed from Open Issues | [ea06eaa] |
|
||||
| 2026-10-11 | Proposed | Jens Tirsvad Nielsen | S01 | Added MIL-007 (quality checks for C++ and C#) | [b74ee0e] |
|
||||
| 2026-10-11 | Accepted | Jens Tirsvad Nielsen | S01 | Added MIL-007 (quality checks for C++ and C#); reviewed (RC-053) | pending |
|
||||
|
||||
---
|
||||
|
||||
@@ -22,7 +22,7 @@ workflows. The Business Case sets no deadline, so the dates are the plan's own;
|
||||
|
||||
## Planning Assumptions
|
||||
|
||||
- Week 1 starts 2026-10-05; phases are two weeks long; the last decision is 2026-12-26; MIL-007 follows in January 2027 (proposed, 2027-01-04 to 2027-01-16).
|
||||
- Week 1 starts 2026-10-05; phases are two weeks long; the last decision is 2026-12-26; MIL-007 follows in January 2027 (2027-01-04 to 2027-01-16, confirmed on 2026-10-11 by S01).
|
||||
- Work on a milestone starts only after its `MIL-*` document is `Accepted`.
|
||||
- Dates were confirmed on 2026-10-10 by S01, standing in for S05 (ADR-0002).
|
||||
|
||||
|
||||