# Review Record: PP-001 Project Plan
|
||||
|
||||
## Metadata
|
||||
| Key | Value |
|
||||
| --- | --- |
|
||||
| ID | RC-002 |
|
||||
| CrossReference | [PP-001], [BC-001] |
|
||||
|
||||
## Version History
|
||||
| Date | Status | Author | Reviewer | Change | Commit |
|
||||
| --- | --- | --- | --- | --- | --- |
|
||||
| 2026-10-10 | Proposed | Jens Tirsvad Nielsen | S05 | Initial version | pending |
|
||||
|
||||
---
|
||||
|
||||
## Artifact Under Review
|
||||
|
||||
- Instance reviewed: [PP-001]
|
||||
- Checklist used: none: the Project Plan has no QC checklist (catalog and `PP.md` reference). Validated against the Business Case [BC-001] constraints and the Go / No-Go criteria of each listed milestone, as `PP.md` prescribes.
|
||||
|
||||
## Checklist Results
|
||||
|
||||
| # | Criterion | Status | Evidence/Notes |
|
||||
| --- | --- | --- | --- |
|
||||
| 1 | Every milestone in the plan has a `MIL-*` document and the plan's dates equal that document's target date | Pass | MIL-001 to MIL-004 exist; decision dates 2026-10-17, 10-31, 11-14, 11-28 match the Target Date of each milestone. |
|
||||
| 2 | Every Business Case scope item is covered by a gateway | Pass | Scope Coverage maps validation, documentation, quality checks and release to MIL-001 to MIL-004. |
|
||||
| 3 | The schedule respects the Business Case constraints | Pass | The Business Case sets no deadline; the plan states its dates are proposals. The constraint that nothing is written before a milestone is accepted is repeated in Planning Assumptions. |
|
||||
| 4 | Dependencies between milestones are stated | Pass | Dependencies section gives MIL-001 to MIL-002 to MIL-003 to MIL-004. |
|
||||
| 5 | Every gateway has an owner who is a stakeholder ID | Pass | All four gateways are owned by S05. |
|
||||
| 6 | Plan content is consistent with the revised mirror behaviour | Pass | UC candidate 1 now describes no GitHub mirror as a successful skip and several mirrors as a failure. |
|
||||
| 7 | Open Issues are current | Fail | Open Issues still lists the decisions for MIL-001 task 1 and task 3 as open; both were decided and recorded in MIL-001. |
|
||||
|
||||
## Overall Verdict
|
||||
|
||||
Go — S01 gave the Go in chat on 2026-10-10 for the revision to UC candidate 1. One stale entry in Open Issues does not affect the schedule or the changed use case; it is recorded as an action item. The author and the approving reviewer are the same person (S01); independent review by S05 is recorded in RC-001 and applies here too.
|
||||
|
||||
## Action Items
|
||||
|
||||
| Action | Owner | Due |
|
||||
| --- | --- | --- |
|
||||
| Remove the answered MIL-001 task 1 and task 3 items from Open Issues in PP-001, with a Version History row | S01 | 2026-10-17 |
|
||||
| Confirm the proposed dates and the start week (already listed in Open Issues) | S01 | 2026-10-17 |
|
||||
|
||||
---
|
||||
|
||||
[PP-001]: ../../project-plan.md
|
||||
[BC-001]: ../../business-case.md
|
||||