Review and accept BC-001, PP-001 and MIL-005 (RC-008 to RC-010)

Add review records, fix the last decision date in PP-001 and update TM-001.
This commit is contained in:
2026-10-10 08:27:37 +08:00
parent 49a5b0ef8e
commit ae4e257236
8 changed files with 160 additions and 15 deletions
+3 -4
View File
@@ -9,8 +9,8 @@
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | UC candidate 1: no GitHub mirror is a successful skip | [0c06789] |
| 2026-10-10 | Proposed | Jens Tirsvad Nielsen | S01 | Added gateway MIL-005 (wiki and translations) | [08ef26a] |
| 2026-10-10 | Deprecated | Jens Tirsvad Nielsen | S01 | Added gateway MIL-005 (wiki and translations) | [08ef26a] |
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | Last decision date is 2026-12-12 after adding MIL-005 | pending |
---
@@ -22,7 +22,7 @@ workflows. The Business Case sets no deadline, so the dates are proposals.
## Planning Assumptions
- Week 1 starts 2026-10-05; phases are two weeks long; the last decision is 2026-11-28.
- Week 1 starts 2026-10-05; phases are two weeks long; the last decision is 2026-12-12.
- Work on a milestone starts only after its `MIL-*` document is `Accepted`.
- Dates are proposed by the author and need confirmation by S01 and S05.
@@ -251,5 +251,4 @@ no tests, no release process.
[Milestone MIL-002]: https://git.tirsystem.com/TirSystem/github-action/milestone/19
[Milestone MIL-003]: https://git.tirsystem.com/TirSystem/github-action/milestone/20
[Milestone MIL-004]: https://git.tirsystem.com/TirSystem/github-action/milestone/21
[0c06789]: https://git.tirsystem.com/TirSystem/github-action/commit/0c06789a2779382672712cd483f4964b28a0ebe9
[08ef26a]: https://git.tirsystem.com/TirSystem/github-action/commit/08ef26a6d3eb98c066b45634c2271e578e6c0a0b