Tirsvad 0b0a3b419a Record S02's acceptance of RC-022 to RC-030
- Review records RC-022 to RC-030 are Accepted
- The documents they review are set to Accepted (previous rows Deprecated)
- RC-028 and RC-029: Go-with-conditions becomes Go; the two action items are closed
- OC-001, SD-001 and DCD-001 carry a note that the UC-002 documents supersede the startProjectCreation signature
2026-10-07 16:38:36 +08:00

4.4 KiB

SQA Review Record: MIL-007 and the planning changes it causes

Metadata

Key Value
ID RC-022
CrossReference MIL-007, QC-MIL-001, MIL-006, BC-001, US-001, UC-002, PP-001

Version History

Date Status Author Reviewer Change Commit
2026-10-07 Accepted Jens Tirsvad Nielsen S02 Initial version 1cd27f7

Artifact Under Review

Checklist Results (QC-MIL-001)

# Criterion Status Evidence/Notes
1 A concrete deliverable is defined for every gate Pass The script that fetches the framework's own submodules and starts through a command link, plus the README usage section.
2 Explicit Go/No-Go criteria are stated for each gate Pass Eight criteria, each with an objective Go and No-Go, including every acceptance criterion of US-001.07 and US-002.
3 Dependencies on other milestones are explicitly mapped Pass Depends on MIL-003 (the framework step and README exist), with the reason.
4 Each milestone is traceable to a Business Case objective or KPI Pass Objectives 5, 7 and 11 and success criterion 11 of BC-001; US-001.07 and US-002.
5 Milestone owner and approving reviewer are identified Pass Owner S01, approving reviewer S02.
6 Milestone has a defined target date consistent with project constraints Pass 2026-12-11 matches PP-001; the Business Case sets no deadline. A proposal for S01 to confirm.

Change checks on the other artifacts

Artifact Change Status Evidence/Notes
MIL-006 AGPL-3.0 default only when GitHub is chosen and the project is public (purpose, order, criterion 3, tasks 1 and 4) Pass Criterion 3 is objective in both directions: AGPL-3.0 on a private project is a No-Go, and so is none on a public project with GitHub. Tasks and tests follow.
BC-001 Objectives 2, 5, 10, 11; scope items; success criteria 10 and 11 Pass Objective 2 and criterion 10 name the public-only default; objective 11 and criterion 11 are new and measurable.
US-001 US-001.06 reworded; US-001.07 and US-002 added; story count updated Pass Given/when/then; each traces to its use case and milestone; INVEST exceptions stated.
PP-001 Phase MIL-007, dependency chain, timeline, scope coverage, end date 2026-12-11 Pass Dates agree with MIL-007. One point carried over from earlier plans: the assumption "phase length: two weeks" is not true of MIL-005, MIL-006 and MIL-007, which are one week.
TM-001 Rows for MIL-007 and the UC-002 artifacts Pass Upstream and downstream columns agree with the CrossReference of each document.

Overall Verdict

Go — MIL-007 meets every mandatory criterion and the changes to the other artifacts are consistent. Drafted by Claude Code for S02 against the checklist; the author and reviewer are the same person for now (as in the earlier records). S02 confirmed the verdict on 2026-10-07 and the Version History rows of the reviewed documents were set to Accepted.

Action Items

Action Owner Due
Say in the plan assumptions that the later phases are one week, not two (or correct the phase length) S01 Before MIL-006 starts
Confirm the proposed target date 2026-12-11 S01 Before MIL-007 starts