Files
RepoFoundry/AGENTS.md
T
Tirsvad 424f14f4f5 Plan RepoFoundry: business case, stakeholders, plan, milestones, UC-001
Add the planning baseline for RepoFoundry (create-project.sh), which
creates GitHub and Gitea repositories, a Gitea -> GitHub push mirror and
a local project with the SQA-QC-Framework.

- BC-001 Business Case and SA-001 Stakeholder Analysis (S01, S02, S03)
- PP-001 Project Plan: three phases, 2026-10-05 to 2026-11-13 (proposed)
- MIL-001 Foundation, MIL-002 Repositories and Mirror,
  MIL-003 Scaffold and Release, with 18 task rows
- US-001, UC-001 "Create a new project" and SSD-001
- Registry: PO language en; PP, MIL, US, UC and SSD rows added

Decisions recorded: origin uses HTTPS from GITEA_URL unless the SSH test
on port 10022 passes; S01 and S02 are held by one person for now.

Refs: no issues synced yet (sync-project.sh dry run only)
2026-10-05 12:30:29 +08:00

2.8 KiB

AGENTS.md

This project uses the SQA and QC framework mounted at framework/.

For any document under docs/ (create, edit or review) use the artifact skill. For planning a project or a phase into tasks, and syncing phases and tasks to Gitea/GitHub as Milestones and Issues, use the project-planning skill. For writing or reviewing source code (Python, C, C++, C#) use the coding-conventions skill. Skills are read from .agents/skills/ (this harness and Codex CLI) and .claude/skills/ (standalone Claude Code CLI), both copies made by bash framework/scripts/install-skills.sh — re-run it after updating the framework.

Never commit, push or open a PR unless asked. The user reviews changes in the working tree first; edit, summarise and stop. The commit/PR rules below apply once a commit has been asked for.

Workflow order

Business Case, Stakeholder Analysis, Project Plan, milestones, tasks synced as issues, then code. Nothing goes under src/ or tests/ unless a milestone document (MIL-*) is accepted and the task is a row in it (ideally a synced issue). If those are missing, plan with the project-planning skill, show the dry-run output of bash framework/scripts/sync-project.sh, and stop. The rule is defined once in framework/process/plan-first-gate.md.

A "build X" request is planning-first: produce the plan and issues, then ask for a go-ahead. Only the user can waive the plan, in chat, for that request. Before planning, find the Product Owner's language (the prompt, or the Languages section of docs/artifact-registry.md); if neither states it, ask.

To enforce the gate at commit time, run bash framework/scripts/install-git-hooks.sh --enable-plan-gate: a commit that changes src/ or tests/ then needs a Task: MIL-NNN#N trailer.

Rules that apply to every document:

  1. Get the short name from framework/registry/artifact-catalog.md and the next version from docs/artifact-registry.md. Create files with bash framework/scripts/new-artifact.sh <SHORT>.
  2. Owners, reviewers and RACI use stakeholder IDs from the project's Stakeholder Analysis, never invented role names.
  3. Every QC criterion is tagged with an ISO/IEC 25010:2023 characteristic.
  4. Every reviewed instance gets an RC-* record in docs/sqa/reviews/.
  5. Do not edit framework/ from this project; propose changes upstream.
  6. Every PR description closes the issues its work completes, one Closes #N per line (Refs #N for partial work); see the project-planning skill.
  7. Every document's ## Version History has Change and Commit columns and keeps the two latest rows. After committing, run framework/scripts/resolve-pending-commits.sh and commit the result before opening the PR (no amend). Never ask for or perform the merge: a reviewer merges.