| 1 |
A concrete deliverable is defined for every gate |
Pass |
The complete script, the README and a written final review with the external prerequisites. |
| 2 |
Explicit Go/No-Go criteria are stated for each gate |
Pass |
Eight criteria, each with an objective Go and No-Go (including all acceptance criteria of US-001.03). Criterion 2 now names the framework URL; it said only the configured URL, which no configuration key defines. Fixed during this review. |
| 3 |
Dependencies on other milestones are explicitly mapped |
Pass |
Depends on MIL-002, with the reason. |
| 4 |
Each milestone is traceable to a Business Case objective or KPI |
Pass |
Maps to Business Case objectives 4 to 7, success criteria 1, 5, 6 and 7, and US-001.03. |
| 5 |
Milestone owner and approving reviewer are identified |
Pass |
Owner S01, approving reviewer S02. |
| 6 |
Milestone has a defined target date consistent with project constraints |
Pass |
2026-11-13, matches PP-001; the Business Case sets no duration, so nothing conflicts. |