TirsvadandClaude Sonnet 5.5 2a6bb8e8af Plan MIL-004: project details preset in config.env
Add objective 8 to the Business Case, US-001.04, extensions 3a and 3b of
UC-001 and the matching SSD, OC, SD, DM-001 and DM-002 notes. Add the phase
to the Project Plan and the milestone MIL-004 with eight Go/No-Go criteria
and five tasks (issues #27 to #31). Review recorded in RC-018.

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 21:44:10 +08:00

4.2 KiB

SQA Review Record: MIL-004 and the planning change it causes

Metadata

Key Value
ID RC-018
CrossReference MIL-004, QC-MIL-001, US-001, UC-001

Version History

Date Status Author Reviewer Change Commit
2026-10-05 Proposed Jens Tirsvad Nielsen S02 Initial version pending

Artifact Under Review

  • Instance reviewed: MIL-004, and the changes it causes in BC-001, US-001, UC-001, SSD-001, OC-001, SD-001, DM-001, DM-002 and PP-001.
  • Checklist used: QC-MIL-001 for MIL-004. The other artifacts were changed, not created; their change is checked below for consistency with the checklists of their types (user story, use case, SSD, operation contract, sequence diagram, domain model) and with the PP reference.
  • Review date: 2026-10-05

Checklist Results (MIL-004, QC-MIL-001)

# Criterion Status Evidence/Notes
1 A concrete deliverable is defined for every gate Pass The script reads eight optional keys, skips their prompts and marks the source; the example config and the README document the keys; tests cover each key.
2 Explicit Go/No-Go criteria are stated for each gate Pass Eight criteria, each with an objective Go and No-Go, including all acceptance criteria of US-001.04.
3 Dependencies on other milestones are explicitly mapped Pass Depends on [MIL-003], with the reason.
4 Each milestone is traceable to a Business Case objective or KPI Pass Maps to objective 8 and success criterion 8 of BC-001, and to US-001.04.
5 Milestone owner and approving reviewer are identified Pass Owner S01, approving reviewer S02.
6 Milestone has a defined target date consistent with project constraints Pass 2026-11-20 matches PP-001; the Business Case sets no duration, so nothing conflicts. The date is a proposal and is accepted here.

Change checks on the other artifacts

Artifact Change Status Evidence/Notes
BC-001 Objective 8, scope item, success criterion 8 Pass The criterion is measurable (tests with each key set, absent, empty and invalid).
US-001 US-001.04 with four acceptance criteria Pass Given/when/then; traces to UC-001 step 3 and MIL-004; size and INVEST exception recorded.
UC-001 Precondition, step 3 note, extensions 3a and 3b, business rule Pass Extensions name the failure (invalid key) and the outcome (stop before any request, no fallback to asking).
SSD-001 Parameters of provideProjectDetails may come from config.env Pass The message itself is unchanged, so the diagram is unchanged.
OC-001 Preset details are part of the Configuration Pass Postcondition and rule added; no new operation.
SD-001 Note that ConfigLoader reads and validates the preset details Pass The second sequence is unchanged because the arguments are the same whether asked or preset.
DM-001, DM-002 Configuration may hold preset project details Pass Both models changed in the same way and the project model stays consistent with the use-case model, as the project rule requires. Dictionary unchanged: no new term.
PP-001 Phase MIL-004, dependency chain and timeline Pass Dates agree with MIL-004; scope table and Gantt updated.

Overall Verdict

Go — MIL-004 passes every mandatory criterion and the changes to the other artifacts are consistent with each other and with the Business Case. Author and reviewer are the same person for now (S01 and S02 are both held by the Maintainer), so the framework independence rule is not met; re-review when a second person takes S02.

Action Items

Action Owner Due
None - -