Commit Graph
12 Commits
Author SHA1 Message Date
TirsvadandClaude Sonnet 5.5 5b66eff809 Resolve pending commit links for the MIL-006 plan
Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-06 13:43:39 +08:00
TirsvadandClaude Sonnet 5.5 d773fa91df Plan MIL-006: the project license set in config.env
Add objective 10 to the Business Case, US-001.06 and the use case, SSD, OC,
SD, DM-001, DM-002, dictionary, DCD-001 and DCD-002 changes: a license set
in config.env (PROJECT_LICENSE, a Gitea license key or none) applies with or
without GitHub; when absent AGPL-3.0 applies only when GitHub is chosen. It
is never asked, and a license the server does not offer stops the run
before anything is created.

Add milestone MIL-006 (8 Go/No-Go criteria, 4 tasks) and its phase in the
Project Plan. All new rows are Proposed.

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-06 13:43:35 +08:00
TirsvadandClaude Sonnet 5.5 7d202a34dc Resolve pending commit links for the MIL-005 plan
Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-06 12:47:33 +08:00
TirsvadandClaude Sonnet 5.5 ded26a658c Plan MIL-005: ask for missing credentials and create the project .env
Add objective 9 to the Business Case (and amend objective 6 and success
criterion 1: a token may be written only to the new project's .env after a
yes), US-001.05, UC-001 extensions 2b, 9c and 9d, with the SSD, OC, SD,
DM-001, DM-002 and dictionary in step. Add the classes CredentialCollector,
EnvFileWriter and EnvFile to DCD-001 and DCD-002, and both ends'
multiplicities to every association. Restore three lines of SD-001 damaged
by an earlier edit.

Add milestone MIL-005 (9 Go/No-Go criteria, 5 tasks) and its phase in the
Project Plan. Accept the planning set and the two DCDs; reviews recorded in
RC-020 and RC-021.

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-06 12:47:26 +08:00
TirsvadandClaude Sonnet 5.5 de78fb195f Resolve pending commit links for the MIL-004 plan
Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 21:48:24 +08:00
TirsvadandClaude Sonnet 5.5 2a6bb8e8af Plan MIL-004: project details preset in config.env
Add objective 8 to the Business Case, US-001.04, extensions 3a and 3b of
UC-001 and the matching SSD, OC, SD, DM-001 and DM-002 notes. Add the phase
to the Project Plan and the milestone MIL-004 with eight Go/No-Go criteria
and five tasks (issues #27 to #31). Review recorded in RC-018.

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 21:44:10 +08:00
TirsvadandClaude Sonnet 5.5 f34affa071 Resolve pending commit links for RC-017 and MIL-002
Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 21:43:01 +08:00
TirsvadandClaude Sonnet 5.5 613a288dea Fix the defects found by the live end-to-end run, add RC-017
- Close stdin for ssh, git, curl and the framework scripts, so a real ssh
  no longer swallows answers meant for later prompts.
- Count LICENSE and LICENSE + README.md (what Gitea creates) as content
  the script made, so a partly created repository can be reused.
- Document the observed token scopes (write:user for user-owned Gitea
  repositories) and the Gitea README.md in the README.
- Correct criterion 2 of MIL-002 (new Proposed version row).
- Record the run and the final security review as RC-017.
- Tests: stdin regression, initial_only reuse, other files count as
  content, example config needs its address edited.

Task: MIL-003#6
Task: MIL-002#1
Refs #20

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 21:41:47 +08:00
TirsvadandClaude Sonnet 5.5 bc90f10151 Resolve pending commit links in planning documents
Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 13:41:48 +08:00
TirsvadandClaude Sonnet 5.5 02875aee5f Accept planning baseline and UC-001 artifacts
Add the Use Case Diagram, Domain Model (use case and project), Dictionary,
Operation Contract, Sequence Diagram, review records RC-001 to RC-015 and
the Traceability Matrix. Split US-001 into one story per milestone, make
GitHub optional (AGPL license applied when chosen), and accept BC-001,
SA-001, PP-001, UCD-001, US-001, UC-001, SSD-001, DM-001, DM-002, OC-001,
SD-001, DICT-001 and MIL-001 to MIL-003 after review.

Refs: no issues synced yet (sync-project.sh dry run only)

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 13:41:36 +08:00
TirsvadandClaude Sonnet 5.5 fa3beaf1c1 Point commit links at the pushed planning commit
Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
2026-10-05 12:32:32 +08:00
Tirsvad 424f14f4f5 Plan RepoFoundry: business case, stakeholders, plan, milestones, UC-001
Add the planning baseline for RepoFoundry (create-project.sh), which
creates GitHub and Gitea repositories, a Gitea -> GitHub push mirror and
a local project with the SQA-QC-Framework.

- BC-001 Business Case and SA-001 Stakeholder Analysis (S01, S02, S03)
- PP-001 Project Plan: three phases, 2026-10-05 to 2026-11-13 (proposed)
- MIL-001 Foundation, MIL-002 Repositories and Mirror,
  MIL-003 Scaffold and Release, with 18 task rows
- US-001, UC-001 "Create a new project" and SSD-001
- Registry: PO language en; PP, MIL, US, UC and SSD rows added

Decisions recorded: origin uses HTTPS from GITEA_URL unless the SSH test
on port 10022 passes; S01 and S02 are held by one person for now.

Refs: no issues synced yet (sync-project.sh dry run only)
2026-10-05 12:30:29 +08:00