Plan MIL-005: ask for missing credentials and create the project .env

Add objective 9 to the Business Case (and amend objective 6 and success
criterion 1: a token may be written only to the new project's .env after a
yes), US-001.05, UC-001 extensions 2b, 9c and 9d, with the SSD, OC, SD,
DM-001, DM-002 and dictionary in step. Add the classes CredentialCollector,
EnvFileWriter and EnvFile to DCD-001 and DCD-002, and both ends'
multiplicities to every association. Restore three lines of SD-001 damaged
by an earlier edit.

Add milestone MIL-005 (9 Go/No-Go criteria, 5 tasks) and its phase in the
Project Plan. Accept the planning set and the two DCDs; reviews recorded in
RC-020 and RC-021.

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
This commit is contained in:
2026-10-06 12:47:26 +08:00
co-authored by Claude Sonnet 5.5
parent 4c9a1af719
commit ded26a658c
17 changed files with 485 additions and 142 deletions
+11 -7
View File
@@ -4,23 +4,23 @@
| Key | Value |
| --- | --- |
| ID | PP-001 |
| CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004], [US-001] |
| CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004], [MIL-005], [US-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-05 | Accepted | Jens Tirsvad Nielsen | S02 | Stories per phase: US-001.01 to US-001.03<br>Dates accepted | [02875ae] |
| 2026-10-05 | Accepted | Jens Tirsvad Nielsen | S02 | Added phase MIL-004 (proposed dates 2026-11-16 to 2026-11-20) | [2a6bb8e] |
| 2026-10-05 | Deprecated | Jens Tirsvad Nielsen | S02 | Added phase MIL-004 (proposed dates 2026-11-16 to 2026-11-20) | [2a6bb8e] |
| 2026-10-06 | Accepted | Jens Tirsvad Nielsen | S02 | Added phase MIL-005 (proposed dates 2026-11-23 to 2026-11-27) | pending |
---
## Purpose
Schedule the four phases that deliver RepoFoundry (`create-project.sh` and its documentation) in dependency order. The Business Case sets no deadline, so the dates below are proposals for S01 to confirm.
Schedule the five phases that deliver RepoFoundry (`create-project.sh` and its documentation) in dependency order. The Business Case sets no deadline, so the dates below are proposals for S01 to confirm.
## Planning Assumptions
- Week 1 starts 2026-10-05; the plan ends by 2026-11-20 (the last phase is proposed).
- Week 1 starts 2026-10-05; the plan ends by 2026-11-27 (the last phase is proposed).
- Phase length: two weeks.
- S01 and S02 review each phase through a pull request, as described in [SA-001]. For now one person holds both roles.
- The PO language is English, so no translated copies are kept.
@@ -33,6 +33,7 @@ Schedule the four phases that deliver RepoFoundry (`create-project.sh` and its d
| Repositories and Mirror | [MIL-002] | 2026-10-19 to 2026-10-30 | 2026-10-30 | S02 | US-001.02 | GitHub and Gitea repositories and the push mirror | [Milestone 44] |
| Scaffold and Release | [MIL-003] | 2026-11-02 to 2026-11-13 | 2026-11-13 | S01 | US-001.03 | Local project, framework, README, final review | [Milestone 45] |
| Configurable Details | [MIL-004] | 2026-11-16 to 2026-11-20 | 2026-11-20 | S01 | US-001.04 | Project details preset in config.env | |
| Credentials | [MIL-005] | 2026-11-23 to 2026-11-27 | 2026-11-27 | S01 | US-001.05 | Missing credentials asked; project .env | |
```plantuml
@startgantt
@@ -45,6 +46,8 @@ Project starts 2026-10-05
[Scaffold and Release Go/No-Go] happens 2026-11-13
[Configurable Details] starts 2026-11-16 and ends 2026-11-20
[Configurable Details Go/No-Go] happens 2026-11-20
[Credentials] starts 2026-11-23 and ends 2026-11-27
[Credentials Go/No-Go] happens 2026-11-27
@endgantt
```
@@ -59,11 +62,12 @@ Project starts 2026-10-05
| Local directory, remotes, framework submodule, skills, hooks, templates, plan gate | [MIL-003] |
| README and SSH prerequisite documentation | [MIL-003] |
| Project details set in `config.env` instead of asked | [MIL-004] |
| Missing credentials asked; the new project's `.env` | [MIL-005] |
## Dependencies
```
MIL-001 → MIL-002 → MIL-003 → MIL-004
MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005
```
A No-Go moves every later date by the time needed to rework the failed criteria.
@@ -91,10 +95,10 @@ A No-Go moves every later date by the time needed to rework the failed criteria.
[MIL-002]: ./milestones/mil-002-repositories-and-mirror.md
[MIL-003]: ./milestones/mil-003-scaffold-and-release.md
[MIL-004]: ./milestones/mil-004-configurable-details.md
[MIL-005]: ./milestones/mil-005-credentials.md
[US-001]: ./user-stories.md
[UC-001]: ./uc-001/uc.md
[SSD-001]: ./uc-001/ssd.md
[02875ae]: https://git.tirsystem.com/TirSystem-BashScript/repo_foundry/commit/02875aee5f2953473924074eea0056eb31af6b7a
[Milestone 43]: https://git.tirsystem.com/TirSystem-BashScript/RepoFoundry/milestone/43
[Milestone 44]: https://git.tirsystem.com/TirSystem-BashScript/RepoFoundry/milestone/44
[Milestone 45]: https://git.tirsystem.com/TirSystem-BashScript/RepoFoundry/milestone/45