Plan MIL-006: the project license set in config.env
Add objective 10 to the Business Case, US-001.06 and the use case, SSD, OC, SD, DM-001, DM-002, dictionary, DCD-001 and DCD-002 changes: a license set in config.env (PROJECT_LICENSE, a Gitea license key or none) applies with or without GitHub; when absent AGPL-3.0 applies only when GitHub is chosen. It is never asked, and a license the server does not offer stops the run before anything is created. Add milestone MIL-006 (8 Go/No-Go criteria, 4 tasks) and its phase in the Project Plan. All new rows are Proposed. Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
This commit is contained in:
+10
-6
@@ -4,23 +4,23 @@
|
||||
| Key | Value |
|
||||
| --- | --- |
|
||||
| ID | PP-001 |
|
||||
| CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004], [MIL-005], [US-001] |
|
||||
| CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004], [MIL-005], [MIL-006], [US-001] |
|
||||
|
||||
## Version History
|
||||
| Date | Status | Author | Reviewer | Change | Commit |
|
||||
| --- | --- | --- | --- | --- | --- |
|
||||
| 2026-10-05 | Deprecated | Jens Tirsvad Nielsen | S02 | Added phase MIL-004 (proposed dates 2026-11-16 to 2026-11-20) | [2a6bb8e] |
|
||||
| 2026-10-06 | Accepted | Jens Tirsvad Nielsen | S02 | Added phase MIL-005 (proposed dates 2026-11-23 to 2026-11-27) | [ded26a6] |
|
||||
| 2026-10-06 | Proposed | Jens Tirsvad Nielsen | S02 | Added phase MIL-006 (proposed dates 2026-11-30 to 2026-12-04) | pending |
|
||||
|
||||
---
|
||||
|
||||
## Purpose
|
||||
|
||||
Schedule the five phases that deliver RepoFoundry (`create-project.sh` and its documentation) in dependency order. The Business Case sets no deadline, so the dates below are proposals for S01 to confirm.
|
||||
Schedule the six phases that deliver RepoFoundry (`create-project.sh` and its documentation) in dependency order. The Business Case sets no deadline, so the dates below are proposals for S01 to confirm.
|
||||
|
||||
## Planning Assumptions
|
||||
|
||||
- Week 1 starts 2026-10-05; the plan ends by 2026-11-27 (the last phase is proposed).
|
||||
- Week 1 starts 2026-10-05; the plan ends by 2026-12-04 (the last phase is proposed).
|
||||
- Phase length: two weeks.
|
||||
- S01 and S02 review each phase through a pull request, as described in [SA-001]. For now one person holds both roles.
|
||||
- The PO language is English, so no translated copies are kept.
|
||||
@@ -34,6 +34,7 @@ Schedule the five phases that deliver RepoFoundry (`create-project.sh` and its d
|
||||
| Scaffold and Release | [MIL-003] | 2026-11-02 to 2026-11-13 | 2026-11-13 | S01 | US-001.03 | Local project, framework, README, final review | [Milestone 45] |
|
||||
| Configurable Details | [MIL-004] | 2026-11-16 to 2026-11-20 | 2026-11-20 | S01 | US-001.04 | Project details preset in config.env | |
|
||||
| Credentials | [MIL-005] | 2026-11-23 to 2026-11-27 | 2026-11-27 | S01 | US-001.05 | Missing credentials asked; project .env | |
|
||||
| Project License | [MIL-006] | 2026-11-30 to 2026-12-04 | 2026-12-04 | S01 | US-001.06 | PROJECT_LICENSE in config.env | |
|
||||
|
||||
```plantuml
|
||||
@startgantt
|
||||
@@ -48,6 +49,8 @@ Project starts 2026-10-05
|
||||
[Configurable Details Go/No-Go] happens 2026-11-20
|
||||
[Credentials] starts 2026-11-23 and ends 2026-11-27
|
||||
[Credentials Go/No-Go] happens 2026-11-27
|
||||
[Project License] starts 2026-11-30 and ends 2026-12-04
|
||||
[Project License Go/No-Go] happens 2026-12-04
|
||||
@endgantt
|
||||
```
|
||||
|
||||
@@ -63,11 +66,12 @@ Project starts 2026-10-05
|
||||
| README and SSH prerequisite documentation | [MIL-003] |
|
||||
| Project details set in `config.env` instead of asked | [MIL-004] |
|
||||
| Missing credentials asked; the new project's `.env` | [MIL-005] |
|
||||
| Project license set in `config.env` | [MIL-006] |
|
||||
|
||||
## Dependencies
|
||||
|
||||
```
|
||||
MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005
|
||||
MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006
|
||||
```
|
||||
|
||||
A No-Go moves every later date by the time needed to rework the failed criteria.
|
||||
@@ -96,11 +100,11 @@ A No-Go moves every later date by the time needed to rework the failed criteria.
|
||||
[MIL-003]: ./milestones/mil-003-scaffold-and-release.md
|
||||
[MIL-004]: ./milestones/mil-004-configurable-details.md
|
||||
[MIL-005]: ./milestones/mil-005-credentials.md
|
||||
[MIL-006]: ./milestones/mil-006-project-license.md
|
||||
[US-001]: ./user-stories.md
|
||||
[UC-001]: ./uc-001/uc.md
|
||||
[SSD-001]: ./uc-001/ssd.md
|
||||
[Milestone 43]: https://git.tirsystem.com/TirSystem-BashScript/RepoFoundry/milestone/43
|
||||
[Milestone 44]: https://git.tirsystem.com/TirSystem-BashScript/RepoFoundry/milestone/44
|
||||
[Milestone 45]: https://git.tirsystem.com/TirSystem-BashScript/RepoFoundry/milestone/45
|
||||
[2a6bb8e]: https://git.tirsystem.com/TirSystem-BashScript/repo_foundry/commit/2a6bb8e8afadfe6ca4a621da30e44a372898ca62
|
||||
[ded26a6]: https://git.tirsystem.com/TirSystem-BashScript/repo_foundry/commit/ded26a658c666bf29d84093cb352e3635e07719b
|
||||
|
||||