Plan RepoFoundry: business case, stakeholders, plan, milestones, UC-001
Add the planning baseline for RepoFoundry (create-project.sh), which creates GitHub and Gitea repositories, a Gitea -> GitHub push mirror and a local project with the SQA-QC-Framework. - BC-001 Business Case and SA-001 Stakeholder Analysis (S01, S02, S03) - PP-001 Project Plan: three phases, 2026-10-05 to 2026-11-13 (proposed) - MIL-001 Foundation, MIL-002 Repositories and Mirror, MIL-003 Scaffold and Release, with 18 task rows - US-001, UC-001 "Create a new project" and SSD-001 - Registry: PO language en; PP, MIL, US, UC and SSD rows added Decisions recorded: origin uses HTTPS from GITEA_URL unless the SSH test on port 10022 passes; S01 and S02 are held by one person for now. Refs: no issues synced yet (sync-project.sh dry run only)
This commit is contained in:
@@ -0,0 +1,90 @@
|
||||
# Project Plan
|
||||
|
||||
## Metadata
|
||||
| Key | Value |
|
||||
| --- | --- |
|
||||
| ID | PP-001 |
|
||||
| CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002], [MIL-003], [US-001] |
|
||||
|
||||
## Version History
|
||||
| Date | Status | Author | Reviewer | Change | Commit |
|
||||
| --- | --- | --- | --- | --- | --- |
|
||||
| 2026-10-05 | Proposed | Jens Tirsvad Nielsen | S02 | Initial version | pending |
|
||||
|
||||
---
|
||||
|
||||
## Purpose
|
||||
|
||||
Schedule the three phases that deliver RepoFoundry (`create-project.sh` and its documentation) in dependency order. The Business Case sets no deadline, so the dates below are proposals for S01 to confirm.
|
||||
|
||||
## Planning Assumptions
|
||||
|
||||
- Week 1 starts 2026-10-05; the plan ends by 2026-11-13.
|
||||
- Phase length: two weeks.
|
||||
- S01 and S02 review each phase through a pull request, as described in [SA-001]. For now one person holds both roles.
|
||||
- The PO language is English, so no translated copies are kept.
|
||||
|
||||
## Gateway Schedule
|
||||
|
||||
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|
||||
| --- | --- | --- | --- | --- | --- | --- | --- |
|
||||
| Foundation | [MIL-001] | 2026-10-05 to 2026-10-16 | 2026-10-16 | S01 | US-001.01 | Safe skeleton, config parsing, prompts, tests | |
|
||||
| Repositories and Mirror | [MIL-002] | 2026-10-19 to 2026-10-30 | 2026-10-30 | S02 | US-001.01 | GitHub and Gitea repositories and the push mirror | |
|
||||
| Scaffold and Release | [MIL-003] | 2026-11-02 to 2026-11-13 | 2026-11-13 | S01 | US-001.01 | Local project, framework, README, final review | |
|
||||
|
||||
```plantuml
|
||||
@startgantt
|
||||
Project starts 2026-10-05
|
||||
[Foundation] starts 2026-10-05 and ends 2026-10-16
|
||||
[Foundation Go/No-Go] happens 2026-10-16
|
||||
[Repositories and Mirror] starts 2026-10-19 and ends 2026-10-30
|
||||
[Repositories and Mirror Go/No-Go] happens 2026-10-30
|
||||
[Scaffold and Release] starts 2026-11-02 and ends 2026-11-13
|
||||
[Scaffold and Release Go/No-Go] happens 2026-11-13
|
||||
@endgantt
|
||||
```
|
||||
|
||||
## Scope Coverage
|
||||
|
||||
| Business Case scope item | Gateway |
|
||||
| --- | --- |
|
||||
| Safe parsing of `config.env` and `.env`, tool checks, prompts, `.gitignore` | [MIL-001] |
|
||||
| Project name check on GitHub | [MIL-001] |
|
||||
| Creation of both repositories and the push mirror | [MIL-002] |
|
||||
| Partial-failure reporting | [MIL-002] |
|
||||
| Local directory, remotes, framework submodule, skills, hooks, templates, plan gate | [MIL-003] |
|
||||
| README and SSH prerequisite documentation | [MIL-003] |
|
||||
|
||||
## Dependencies
|
||||
|
||||
```
|
||||
MIL-001 → MIL-002 → MIL-003
|
||||
```
|
||||
|
||||
A No-Go moves every later date by the time needed to rework the failed criteria.
|
||||
|
||||
## Plan Risks
|
||||
|
||||
| Risk | Impact | Mitigation |
|
||||
| --- | --- | --- |
|
||||
| No disposable GitHub organization for testing | Organization-owner path untested | Agree the test owners before [MIL-002] starts |
|
||||
| Gitea API behaviour differs from the swagger on the live server | Mirror task takes longer | Test against `git.tirsystem.com` early in [MIL-002] |
|
||||
|
||||
## Open Issues
|
||||
|
||||
- Confirm the proposed dates (S01).
|
||||
- Decided: `origin` uses HTTPS derived from `GITEA_URL`, unless the SSH test passed, in which case it uses SSH on port 10022.
|
||||
- Decided: use case [UC-001] "Create a new project" is created, with [SSD-001]; tasks that implement its steps reference it.
|
||||
- Decided: S01 and S02 are both held by one person for now.
|
||||
- Open: this plan says the script does not make the first commit; confirm.
|
||||
|
||||
---
|
||||
|
||||
[BC-001]: ./business-case.md
|
||||
[SA-001]: ./stakeholder-analysis.md
|
||||
[MIL-001]: ./milestones/mil-001-foundation.md
|
||||
[MIL-002]: ./milestones/mil-002-repositories-and-mirror.md
|
||||
[MIL-003]: ./milestones/mil-003-scaffold-and-release.md
|
||||
[US-001]: ./user-stories.md
|
||||
[UC-001]: ./uc-001/uc.md
|
||||
[SSD-001]: ./uc-001/ssd.md
|
||||
Reference in New Issue