Accept planning baseline and UC-001 artifacts

Add the Use Case Diagram, Domain Model (use case and project), Dictionary,
Operation Contract, Sequence Diagram, review records RC-001 to RC-015 and
the Traceability Matrix. Split US-001 into one story per milestone, make
GitHub optional (AGPL license applied when chosen), and accept BC-001,
SA-001, PP-001, UCD-001, US-001, UC-001, SSD-001, DM-001, DM-002, OC-001,
SD-001, DICT-001 and MIL-001 to MIL-003 after review.

Refs: no issues synced yet (sync-project.sh dry run only)

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
This commit is contained in:
2026-10-05 13:41:36 +08:00
co-authored by Claude Sonnet 5.5
parent fa3beaf1c1
commit 02875aee5f
32 changed files with 1666 additions and 73 deletions
+6 -5
View File
@@ -9,7 +9,8 @@
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-05 | Proposed | Jens Tirsvad Nielsen | S02 | Initial version | [424f14f] |
| 2026-10-05 | Deprecated | Jens Tirsvad Nielsen | S02 | Initial version | [424f14f] |
| 2026-10-05 | Accepted | Jens Tirsvad Nielsen | S02 | Stories per phase: US-001.01 to US-001.03<br>Dates accepted | pending |
---
@@ -29,8 +30,8 @@ Schedule the three phases that deliver RepoFoundry (`create-project.sh` and its
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Foundation | [MIL-001] | 2026-10-05 to 2026-10-16 | 2026-10-16 | S01 | US-001.01 | Safe skeleton, config parsing, prompts, tests | |
| Repositories and Mirror | [MIL-002] | 2026-10-19 to 2026-10-30 | 2026-10-30 | S02 | US-001.01 | GitHub and Gitea repositories and the push mirror | |
| Scaffold and Release | [MIL-003] | 2026-11-02 to 2026-11-13 | 2026-11-13 | S01 | US-001.01 | Local project, framework, README, final review | |
| Repositories and Mirror | [MIL-002] | 2026-10-19 to 2026-10-30 | 2026-10-30 | S02 | US-001.02 | GitHub and Gitea repositories and the push mirror | |
| Scaffold and Release | [MIL-003] | 2026-11-02 to 2026-11-13 | 2026-11-13 | S01 | US-001.03 | Local project, framework, README, final review | |
```plantuml
@startgantt
@@ -72,11 +73,11 @@ A No-Go moves every later date by the time needed to rework the failed criteria.
## Open Issues
- Confirm the proposed dates (S01).
- Decided: the proposed dates are accepted with this plan (S01 asked for its acceptance on 2026-10-05); a change needs a new Version History row.
- Decided: `origin` uses HTTPS derived from `GITEA_URL`, unless the SSH test passed, in which case it uses SSH on port 10022.
- Decided: use case [UC-001] "Create a new project" is created, with [SSD-001]; tasks that implement its steps reference it.
- Decided: S01 and S02 are both held by one person for now.
- Open: this plan says the script does not make the first commit; confirm.
- Open: this plan says the script does not make the first commit; confirm before MIL-003 starts.
---